Analysis of time and cost additions in public works contracts: a case study in Pernambuco-Brazil

Authors

DOI:

https://doi.org/10.46421/entac.v21i1.8626

Keywords:

Planning, Time, Cost, Public work, Contracts

Abstract

This study aimed to identify the factors that most contribute to contract modifications. The methodology combined qualitative and quantitative approaches through a case study involving seven public construction contracts executed in the state of Pernambuco, Brazil, between 2014 and 2024, along with simple linear regression analysis to assess the influence of the bidding discount rate, defined as the percentage discount offered during the procurement process. The results indicated that 64% of contract amendments were attributable to deficiencies in the planning and design stages (Category A: design errors), 11% resulted from failures during project execution (Category B: construction execution failures), and 25% were associated with unforeseen events (Category C: unforeseen conditions). The statistical analysis revealed a moderate correlation between the bidding discount rate and cost amendments (R=0.4804; R² = 23.08%), whereas the correlation with time extensions was very weak and negative (R=-0.2418; R²=5.85%). Finally, the study enabled the development of a best-practices checklist to support contract management in public construction projects.

Author Biographies

  • Lucas Nóbrega Nunes Cavalcanti , Polytechnic School of the University of Pernambuco

    He studied at Colégio Damas. Currently, he is an Engineering Assistant at Nunes & Cavalcanti Construções LTDA. He has experience in the field of Civil Engineering, with an emphasis on Civil Construction (Recife - PE, Brazil).

  • Júlia Cavalcante Samico, Polytechnic School of the University of Pernambuco

    Assistant in urban infrastructure works and in works auditing. Currently a Civil Engineering undergraduate student at the Polytechnic School of the University of Pernambuco, working in the Research Group in Engineering Applied to the Environment and as a monitor for the Construction Equipment discipline, both linked to the university, and in addition, she is an intern at Planum Empreendimentos, a company focused on the Minha Casa, Minha Vida program, working in the quality area (Recife - PE, Brazil).

  • Eliane Maria Gorga Lago, Polytechnic School of the University of Pernambuco

    Holds a PhD from the Doctoral Program in Industrial and Systems Engineering at the University of Minho, UMinho, Portugal. Currently, she is an adjunct professor, vice-coordinator of the Bachelor's degree in Civil Engineering, coordinator of the Occupational Safety and Hygiene Laboratory, and coordinator of the Occupational Safety and Hygiene specialization, all at the Polytechnic School of the University of Pernambuco. She is also a member of the Occupational Safety and Health Committee of the University of Pernambuco, participating in various projects in the areas of Safety Engineering with the development of active technologies, partnering with funding agencies and private companies. She also works in the area of ​​real estate appraisals (Recife - PE, Brazil).

  • Adolpho Guido de Araújo, Polytechnic School of the University of Pernambuco

    PhD in Civil Engineering from the Postgraduate Program in Civil Engineering, specializing in Structures with an emphasis on Civil Construction, at the Federal University of Pernambuco. Currently participates in the BIM Decision Support Research Group at UFPE, is a researcher at the Technical Profile Laboratory at UFPE, and is an Adjunct Professor in the Civil Engineering Course at UPE (Recife - PE, Brazil).

References

BROZOVSKY, J.; LABONNOTE, N.; VIGREN, O. Digital Technologies in Architecture, Engineering, and Construction. Autom. Constr., 158, 2024.

OCHOA, W.A.A. Análise dos Fatores da Complexidade na Indústria Da Construção e sua Relação com a Gestão de Projetos. Dissertação (Mestrado), Universidade Tecnológica Federal do Paraná (UTFPR), Curitiba, 2023.

DRESCH, A.; VEIT, D.R.; LIMA, P.N. de; LACERDA, D.P.; COLLATTO, D.C. Inducing Brazilian Manufacturing SMEs Productivity with Lean Tools. International Journal of Productivity and Performance Management, v.68, p. 69–87, 2019. Disponível em: doi:10.1108/IJPPM-10-2017-0248.

INSTITUTO BRASILEIRO DE GEOGRAFIA E ESTATÍSTICA. Em 2022, Ocupação na indústria da construção cresce 4,4% e serviços especializados ganham participação no valor de obra do setor. versão online. Disponível em: https://agenciadenoticias.ibge.gov.br. Acesso em: 8 maio de 2025.

ALVARENGA, F.C.; MAUÉS, L.M.F.; SANTOS JÚNIOR, P.C. dos; MACEDO, A.N. Alterações de Custo e Prazo Em Obras Públicas. Ambiente Construído, v. 21, p. 161–180, 2021. Disponível em: doi:10.1590/s1678-86212021000100500.

BRASIL. Lei no 14.133, de 10 de Abril de 2021. Nova Lei de Licitações e Contratos Administrativos (Lei No 14.133/2021); 2a Edição; Senado Federal: Brasília, DF, 2022.

BRASIL. Lei No 8.666, de 21 de junho de 1993. Institui normas para licitações e contratos da administração pública (Lei nº 8666/1993), Congresso Nacional: Brasília, DF, 1993.

SCARPATI, R.N.; CORREIA, R.D. Fatores Que Influenciam No Desconto Obtido Em Obras e Serviços de Engenharia. Revista de Gestão e Secretariado, v. 13, p. 1868–1889, 2022. Disponível em: doi:10.7769/gesec.v13i3.1449.

FRISON, C.B.; FERNANDES MARCHIORI, F.; WATASHI, D.B. Dos Altos Descontos à Superação de Custos: O “Efeito Pêndulo” Em Licitações de Obras Públicas. In: XX Encontro Nacional de Tecnologia do Ambiente Construído; Associação Nacional do Ambiente Construído: Maceió, Anais [...]. 2024. p. 1–12.

DIAS, S.F. Critérios Para Seleção de Licitantes de Obras Públicas Evitando Contratações a Preços Inexequíveis. Tese (Doutorado), Universidade Federal de Santa Catarina: Florianópolis, 2021.

CORRÊA, B. dos S.; SHIH, H.H.O.M. Gestão Da Obra Pública: Uma Análise Comparativa Dos Aditivos de Valor e de Prazo Entre Duas Instituições Federais de Ensino. Revista Gestão Universitária na América Latina – GUAL, p. 130–150, 2019. Disponível em: doi:10.5007/1983-4535.2019v12n3p130.

MONTEIRO, C. de O.; OLIVEIRA, K.P.R. de; RORIZ, R.F.; SANTOS, D. de G. Aditivos Contratuais de Obras Públicas: Causas Ainda Sem Soluções. In: XII Simpósio Brasileiro de Gestão e Economia da Construção; Associação Nacional do Ambiente Construído: Maceió, Anais [...]. 2021. p. 1–8.

OLIVEIRA, D.R. de; SOUTO, E. do N. de Análise Dos Aditivos de Prazo e Valor Dos Contratos de Obras Em Uma Instituição de Ensino Federal. Revista Foco, 17, e3400, 2024. Disponível em: doi:10.54751/revistafoco.v17n5-014.

Published

2026-08-19

How to Cite

CAVALCANTI , L. N. N. et al. Analysis of time and cost additions in public works contracts: a case study in Pernambuco-Brazil. NATIONAL MEETING OF BUILT ENVIRONMENT TECHNOLOGY, v. 21, n. 1, 19 Aug.2026.