Limits of Constraint Anticipation in the Make-Ready Process

Authors

DOI:

https://doi.org/10.46421/entac.v21i1.8724

Keywords:

Last Planner System (LPS ), Planejamento de Médio Prazo, Restrições

Abstract

Lookahead planning plays a central role in the Last Planner System by supporting work preparation and constraint removal. This study analyzes the behavior of constraints in residential projects, considering anticipation in constraint identification and the time required for removal. The research analyzed more than 12,000 constraints collected from 108 residential projects. Constraints were semantically classified and evaluated according to anticipation and removal time. Results indicate a low occurrence of constraints simultaneously identified in advance and quickly resolved. The analysis contributes to understanding the limits of medium-term planning as an anticipation mechanism, highlighting limitations in the preventive effectiveness of the make-ready process.

Author Biographies

  • Raquel Hoffmann Reck, Climb Consulting Group

    PhD in Engineering at UFRGS and Lean Construction Consultant at Climb Consulting Group

  • Marcelo Silva Santos Segundo, Climb Consulting Group

    Mestrando em Engenharia Civil na Universidade Federal do Ceará e Consultor Lean na Climb Consulting Group (Fortaleza - CE, Brasil)

  • Bernardo Martins Beck da Silva Etges, Climb Consulting Group

    Doutorando em Engenharia Civil pela Universidade Federal do Rio Grande do Sul e CEO Climb Consulting Group (Porto Alegre - RS, Brasil)

  • Marcus Costa Tenório Fireman, Climb Consulting Group

    Doutor em Engenharia pela Universidade Federal do Rio Grande do Sul e CEO Climb Consulting Group (Porto Alegre - RS, Brasil)

References

[1] HAMZEH, Farook R.; BALLARD, Glenn; TOMMELEIN, Iris D. Improving construction work flow: the connective role of lookahead planning. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 16., 2008, Manchester. Proceedings […]. Manchester: IGLC, 2008. p. 635-646.

[2] BALLARD, Glenn; HOWELL, Gregory. Shielding production: essential step in production control. Journal of Construction Engineering and Management, Reston, v. 124, n. 1, p. 11-17, 1998.

[3] COELHO, Henrique O.; FORMOSO, Carlos T. Planejamento e controle da produção em nível de médio prazo: funções básicas e diretrizes de implementação. In: SIMPÓSIO BRASILEIRO DE GESTÃO E ECONOMIA DA CONSTRUÇÃO, 4., 2005, Porto Alegre. Anais […]. Porto Alegre: ANTAC, 2005.

[4] KEMMER, Sérgio L.; HEINECK, Luiz F. M.; BRITO, Felipe L.; BEZERRA, Bruno B.; CARDOSO, Hériglys S. Planejamento de médio prazo: contribuição ao gerenciamento do plano com base em aplicação prática. In: ENCONTRO NACIONAL DE TECNOLOGIA DO AMBIENTE CONSTRUÍDO, 11., 2006, Florianópolis. Anais […]. Florianópolis: ANTAC, 2006.

[5] ANGELIM, Vanessa Lira; ALVES, Thais da Costa Lago; LIMA, Mariana Monteiro Xavier de; BARROS NETO, José de Paula. Planejamento de médio prazo: panorama de sua aplicação na construção civil. Ambiente Construído, Porto Alegre, v. 20, n. 1, p. 87-104, jan./mar. 2020.

[6] BELLAVER, Gustavo B.; SANTOS, Diego O. R. S.; ETGES, Bernardo M.; SANTOS, Pablo H. J.; MOTA, Wesley de S. Implementing lookahead planning and digital tools to enable scalability and set of information in a multi-site lean implementation. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 30., 2022, Edmonton. Proceedings […]. Edmonton: IGLC, 2022. p. 750-761.

[7] SPEAR, Steven; BOWEN, H. Kent. Decoding the DNA of the Toyota Production System. Harvard Business Review, Boston, v. 77, n. 5, p. 96–106, Sept./Oct. 1999.

Published

2026-10-01

How to Cite

RECK, R. H. et al. Limits of Constraint Anticipation in the Make-Ready Process. NATIONAL MEETING OF BUILT ENVIRONMENT TECHNOLOGY, v. 21, n. 1, 1 Oct.2026.