Impacts of two-stage mortar façade rendering on project duration and costs
A case study
DOI:
https://doi.org/10.46421/entac.v21i1.8931Keywords:
Construction planning, Line of balance, Mortar façade rendering, Scheduling, Cost managementAbstract
This study aims to analyze the impacts of executing mortar façade rendering in two stages on the planning of a vertical building project located in Uberlândia, Brazil. The research was conducted through a case study in a high-standard residential building, using data provided by the construction company, including schedules, monthly replanning documents, and cost information. The methodology involved analyzing the project’s Line of Balance, identifying the critical path, and evaluating an action plan based on dividing façade execution into two stages. The results showed that the proposed strategy reduced the idle period between activities from 131 to 39 working days and advanced the projected project completion date by 77 days. From a financial perspective, although the strategy increased logistical and operational costs, the reduction in indirect and administrative costs resulted in a net saving of R$ 54,565.34. The study indicates that executing the façade in two stages can contribute to optimizing workflow, reducing delays, and improving planning efficiency in vertical construction projects.
References
[1] BAÍA, Luciana Lyrio; SABBATINI, Fernando Henrique. Projeto e execução de revestimento de argamassa. 4. ed. São Paulo: O Nome da Rosa, 2008.
[2] SABBATINI, Fernando Henrique. Tecnologia de revestimentos argamassados. São Paulo: Escola Politécnica da Universidade de São Paulo, 1998.
[3] BARROS, Mércia Maria Semensato Bottura de. Tecnologia de produção de revestimentos de argamassa. São Paulo: Escola Politécnica da Universidade de São Paulo, 2001.
[4] KELLEY, James E.; WALKER, Morgan R. Critical-path planning and scheduling. In: Proceedings of the Eastern Joint Computer Conference. Boston: ACM, 1959. p. 160–173. DOI: https://doi.org/10.1145/1460299.1460318.
[5] CARRARO, Marília; OLIVEIRA, Luciana Alves. Os impactos do processo de projeto na execução e desempenho da fachada. In: SIMPÓSIO BRASILEIRO DE QUALIDADE DO PROJETO NO AMBIENTE CONSTRUÍDO, 2015. p. 1161–1172. DOI: https://doi.org/10.18540/2176-4549.6056.
[6] BERNARDES, Maurício Moreira e Silva. Planejamento e controle da produção para empresas de construção civil. 2. ed. Rio de Janeiro: LTC, 2021.
[7] MATTOS, Aldo Dórea. Planejamento e controle de obras. 2. ed. São Paulo: Pini, 2019.
[8] ARDITI, David; TOKDEMIR, Onur Behzat; SUH, Kangsuk. Effect of learning on line-of-balance scheduling. International Journal of Project Management, v. 19, n. 5, p. 265–277, 2001. DOI: https://doi.org/10.1016/S0263-7863(99)00079-4.
[9] KENLEY, Russell; SEPPÄNEN, Olli. Location-Based Management for Construction: Planning, Scheduling and Control. London: Spon Press, 2010.
[10] KOSKELA, Lauri. Application of the New Production Philosophy to Construction. Stanford: Center for Integrated Facility Engineering (CIFE), Stanford University, 1992.
[11] HOWELL, Gregory. What is Lean Construction? In: Proceedings of the 7th Annual Conference of the International Group for Lean Construction. Berkeley, 1999. DOI: https://doi.org/10.24928/1999/0262.
[12] DOURADO, Gustavo Henrique de Oliveira; SERRA, Sheyla Mara Baptista; LORENZON, Itamar Aparecido. Protocolo para execução de revestimentos argamassados de fachadas. In: SIMPÓSIO BRASILEIRO DE GESTÃO E ECONOMIA DA CONSTRUÇÃO, 12., 2021, Porto Alegre. Anais [...]. Porto Alegre: ANTAC, 2021. p. 1–8. DOI: https://doi.org/10.46421/sibragec.v12i00.499
[13] BIOTTO, Clarissa Notariano. Método para projeto e planejamento de sistemas de produção na construção civil com uso da modelagem BIM 4D. 2012. Dissertação (Mestrado em Engenharia Civil) – Programa de Pós-Graduação em Engenharia Civil, Universidade Federal do Rio Grande do Sul, Porto Alegre, 2012.
[14] GOMES, André; OLIVEIRA, Luciana Alves; HEINECK, Luiz Fernando Mahlmann. Representações gráficas para uma visão conjunta de Lean Construction e Linha de Balanço. In: SIMPÓSIO BRASILEIRO DE GESTÃO E ECONOMIA DA CONSTRUÇÃO, 2021. Anais [...]. 2021.
[15] GLOVACKI, Marcelo; OSCAR, Luiz Henrique Costa. Linha de balanço: aplicações e seus prós e contras para a construção civil. Revista Boletim do Gerenciamento, Rio de Janeiro, n. 44, p. 87–95, 2024.