The decoupling between formal management and operational execution in industrial megaprojects: A narrative review
DOI:
https://doi.org/10.46421/entac.v21i1.8959Keywords:
Decoupling, Megaprojects, Industrial piping, Institutional theory, ComplexityAbstract
Industrial megaprojects adopt established management systems, yet a divergence persists between formal planning and operational execution. This article investigates the causes of this decoupling in industrial piping assembly, a critical-path service with rigid sequential interdependence. Through a narrative review, with a search in the Scopus database and a thematic analysis of 17 articles and 7 seminal works, three causal dimensions were identified: (1) the adoption of management practices driven more by institutional legitimacy than by operational effectiveness, generating ceremonial activities; (2) the limitations of linear controls — schedules and key performance indicators (KPI) — in the face of the sociotechnical complexity of the construction site; and (3) informal frontline adaptations — improvisation and selective information retention — as rational responses to operational constraints. Methods such as advanced work packaging (AWP), lean construction (LC) and building information modeling (BIM), when implemented under institutional pressure, may widen the gap between management and operations. A multilevel model is proposed, arguing that relaxing formal rules, when uncertainty requires it, should constitute an explicit organizational decision rather than an unrecorded informal practice.
References
REFERÊNCIAS
[1] FLYVBJERG, B. What You Should Know about Megaprojects and Why: An Overview. Project Management Journal, v. 45, n. 2, p. 6–19, abr. 2014.
[2] LOCATELLI, G. et al. The Successful Delivery of Megaprojects: A Novel Research Method. Project Management Journal, v. 48, n. 5, p. 78–94, out. 2017.
[3] RAHIM, A. Causes and Effects of Rework: A Study on a Major Water Supply Pipe-Line Construction Project in Libya. International Journal of Innovation, Management and Technology, p. 460–465, 2017.
[4] ALSHIBANI, A. et al. Identifying and Ranking the Root Causes of Schedule Delays in Oil and Gas Pipeline Construction Projects. Energies, v. 16, n. 1, p. 283, 27 dez. 2022.
[5] MEYER, J. W.; ROWAN, B. Institutionalized Organizations: Formal Structure as Myth and Ceremony. The American Journal of Sociology, v. 83, n. 2, p. 340–363, 1977.
[6] AAMIR, H. et al. Advanced work packaging in construction management through systematic review and socio-technical framework for digital integration. Computer Science Review, v. 60, p. 100856, maio 2026.
[7] IBRAHIM, A. et al. Critical enablers for lean construction diffusion in megaprojects: A framework for sustainable and efficient infrastructure development. Cleaner Engineering and Technology, v. 31, p. 101158, abr. 2026.
[8] IBRAHIM, A. et al. Why lean construction falters in megaprojects: A systemic diagnosis of interdependent barriers using fuzzy DEMATEL. Results in Engineering, v. 30, p. 110746, jun. 2026.
[9] IBRAHIM, A.; ZAYED, T.; LAFHAJ, Z. Trends and gaps in lean construction practices for construction of megaprojects: A critical review. Alexandria Engineering Journal, v. 118, p. 174–193, abr. 2025.
[10] SARHAN, S. et al. Institutional Waste within the UK Construction Procurement Context: A Conceptual Framework. Engineering Project Organization Journal, v. 8, n. 1, p. 18, 25 set. 2024.
[11] DIMAGGIO, P. J.; POWELL, W. W. The Iron Cage Revisited: Institutional Isomorphism and Collective Rationality in Organizational Fields. American Sociological Review, v. 48, n. 2, p. 147, abr. 1983.
[12] ZOMER, T.; NEELY, A.; SAVAGET, P. How do projects decouple from coercive pressures? A study of decoupling in construction projects. International Journal of Managing Projects in Business, v. 17, n. 2, p. 247–277, 19 abr. 2024.
[13] ALQERSHY, M. T.; SHI, Q.; ANBAR, D. R. Analysing the interplay of isomorphic pressures, perceived benefits and top management support on social responsibility performance of Belt and Road megaprojects. Engineering, Construction and Architectural Management, v. 32, n. 6, p. 4074–4099, 3 jun. 2025.
[14] BIESENTHAL, M. et al. Between conformity and change: How institutional forces shape, and are shaped by, projects. International Journal of Project Management, v. 44, n. 2, p. 102828, mar. 2026.
[15] TRIST, E. L.; BAMFORTH, K. W. Some Social and Psychological Consequences of the Longwall Method of Coal-Getting. Human Relations, v. 4, n. 1, p. 3–38, fev. 1951.
[16] CALDERON-TELLEZ, J. A. et al. Project management and system dynamics modelling: Time to connect with innovation and sustainability. Systems Research and Behavioral Science, v. 41, n. 1, p. 3–29, jan. 2024.
[17] LIN, L. et al. Choosing suitable project control modes to improve the knowledge integration under different uncertainties. International Journal of Project Management, v. 37, n. 7, p. 896–911, out. 2019.
[18] SNOWDEN, D. J.; BOONE, M. E. A Leader's Framework for Decision Making. Harvard Business Review, v. 85, p. 68–76, 2007.
[19] CHIPONDE, D.; GLEDSON, B.; GREENWOOD, D. The Institutional Field of Learning From Project-Related Failures: Opportunities and Challenges. Construction Economics and Building, v. 24, n. 1/2, 3 jul. 2024.
[20] AHMETI, M.; SYLEJMANI, M. Analyzing Construction Delays in Post-Conflict Economies: An Empirical Study of Causes and Mitigation Strategies in the Western Balkans. Turkish Journal of Engineering. 2025
[21] CHIPONDE, D. B.; GLEDSON, B.; GREENWOOD, D. Contrasting Perceptions of Construction Managers and Project Managers Around Failure in Light of Morris and Geraldi's Institutional Context. Engineering Project Organization Journal, v. 11, n. 2, p. 20, 25 set. 2024.
[22] SAUNDERS, F. C.; TOWNSEND, E. A. Delivering new nuclear projects: a megaprojects perspective. International Journal of Managing Projects in Business, v. 12, n. 1, p. 144–160, 24 maio 2019.
[23] SYDOW, J.; SCHREYÖGG, G.; KOCH, J. Organizational Path Dependence: Opening the Black Box. Academy of Management Review, v. 34, n. 4, p. 689–709, 1 out. 2009.
[24] ZAMAN, U. et al. Understanding the soft side of software projects: An empirical study on the interactive effects of social skills and political skills on complexity–performance relationship. International Journal of Project Management, v. 37, n. 3, p. 444–460, abr. 2019.