Shared resource management on the assembly line of a modular construction factory
DOI:
https://doi.org/10.46421/entac.v21i1.8972Keywords:
modular construction, Standardized work, Continuos Flow, Continuous improvementAbstract
This study analyzes the standardization of the use of shared resources in an assembly line of a modular construction factory, focusing on the use of the overhead crane from the perspective of Lean Construction and Standardized Work. The research was developed through an action research strategy, involving diagnosis of the production system, mapping of the operational flow, measurement of activity durations, and implementation of improvements in the assembly line. The results showed that the overhead crane was the main critical resource of the production system, being responsible for operational interferences, waiting times, and discontinuities in the production flow. From the standardization of the operational flow of the equipment and the balancing of activities between workstations, a reduction of approximately 25% in the assembly line cycle time was observed. In addition, greater production flow stability, reduction of operational interferences, and improvement in the productive capacity of the system were identified. The study demonstrates that standardizing the use of shared resources contributes to reducing variability and improving operational performance in industrialized construction environments.
References
[1] PAN, W; HON, C K. Briefing: Modular integrated construction for high-rise buildings. Proceedings of the Institution of Civil Engineers: Municipal Engineer, v. 173, n. 2, p. 64–68, 1 jun. 2020.
[2] WUNI, I Y; SHEN, G . Critical success factors for modular integrated construction projects: a review. Building Research and Information, v. 48, n. 7, p. 763–784, 2 out. 2019.
[3] MELLO, M.H.; Strandhagen, J.O.; Alfnes, E. Analyzing the Factors Affecting Coordination in Engineer-to-Order Supply Chain. Int.J. Oper. Prod. Manag. 2015, 35, 1005–1031.
[4] KOSKELA, L. An exploration towards a production theory and its application to construction. Espoo: Helsinki University of Technology, 2000.
[5] LIKER, J. K. The Toyota Way: 14 management principles from the world´s greatest anufacturer. New York: McGraw-Hill, 2004.
[6] BINNINGER, M., DLOUHY, J., & HAGHSHENO, S. (2017). Technical Takt Planning and Takt Control in Construction. IGLC 2017 – Proceedings of the 25th Annual Conference of the Internacional Group for Lean Construction, II(July), 605–612. https://doi.org/10.24928/2017/0297
[7] FORMOSO ET AL. (2021). “Slack in construction – Part 1: core concepts” Proc. 29th Annual Conference of the International Group for Lean Construction (IGLC29), Alarcon, L.F. and González, V.A. (eds.), Lima, Peru, pp. 187–196, doi.org/10.24928/2021/0183, online at iglc.net.
[8] LIKER, J K.; MEIER, David. O Modelo Toyota: manual de aplicação. Porto Alegre: Bookman, 2007.
[9] WUNI, I Y; SHEN, Geoffrey Qiping. Barriers to the adoption of modular integrated construction: Systematic review and meta-analysis, integrated conceptual framework, and strategies. Journal of Cleaner Production, v. 249, p. 119347, 10 mar. 2020
[10] FORMOSO, C. T.; SOMMER, L.; KOSKELA, L.; ISATTO, E. L. The identification and analysis of making-do waste: insights from two Brazilian construction sites. Ambiente Construído, Porto Alegre, v. 17, n. 3, p. 183-197, jul./set. 2017.
[11] KOSKELA, L. Application of the New Production Philosophy to Construction. Stanford: Stanford University, 1992.
[12] MEDEIROS, G. D. Modelo de planejamento e controle da produção para obter estabilidade básica em fábricas de construção modular. 2025. Dissertação (Mestrado em Construção e Infraestrutura) – Universidade Federal do Rio Grande do Sul, Porto Alegre, 2025.
[13] BULHÕES, I R. Diretrizes para implementação de fluxo contínuo na construção civil: uma abordagem baseada na Mentalidade Enxuta. Campinas: UNICAMP, 2009.
[14] THIOLLENT, M. Metodologia da Pesquisa-Ação. 14. ed. São Paulo: Cortez, 2005. 132 p.
[15] SUSMAN, G. I. EVERED, R. D. (1978). An assessment of the scientific merits of action research. Administrative Science Quarterly 23: 582–603
[16] HARRIS, R. B.; IOANNOU, P. G. Scheduling projects with repeating activities. Journal of Construction Engineering and Management, v. 124, n. 4, p. 269-278, 1998.
[17] FIREMAN, M. C. T.; SAURIN, T. A.; FORMOSO, C. T. The role of slack in standardized work in construction: an exploratory study. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 26., 2018, Chennai. IGLC, 2018. p. 1313-1322.
[18] MARION, G. L. C.; SAURIN, T. A.; VIANA, D. D. The cost-benefit of slack in production planning and control in construction projects. Construction Management and Economics, 2025.