What the level of detail reveals: sub-activity flow in cast-in-place concrete walls
DOI:
https://doi.org/10.46421/entac.v21i1.8976Keywords:
Planejamento Baseado em Locais, Linha de balanço, Fluxo de produção, Paredes de concreto moldadas in loco, Planejamento da construçãoAbstract
Activity-based schedules tend to represent the execution of cast-in-place concrete walls as a single work package per repetitive unit, concealing the internal dynamics of sub-activities. This paper analyzes what becomes visible when planning shifts from an aggregated representation (level 1) to a representation detailed by sub-activities (level 2). The research was conducted through an exploratory multiple case study in three residential projects of a repetitive nature. Data were collected through document analysis, semi-structured interviews, and direct field observation. The comparison between the two levels showed that a higher level of detail exposes bottlenecks that are not identifiable in the original planning, workable backlogs informally managed by crews, and internal flow discontinuities between sub-activities. The results indicate that takt time compliance does not necessarily imply continuity of the internal flow within the repetitive unit and confirm the level of detail as a condition for the validity of flow analysis.
References
[1] ARDITI, D.; TOKDEMIR, O. B.; SUH, K. Challenges in Line-of-Balance Scheduling. Journal of Construction Engineering and Management, v. 128, n. 6, p. 545–556, 2002.
[2] KENLEY, R.; SEPPÄNEN, O. Location-based management for construction: Planning, scheduling and control. 1. ed. Abingdon: Spon Press, 2010.
[3] KEMMER, S. L.; HEINECK, L. F. M.; ALVES, T. da C. L. Using the line of balance for production system design. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 16., 2008, Manchester. Proceedings [...]. Manchester: IGLC, 2008. p. 299–308.
[4] KENLEY, R. CME Forum: A response to "Construction Flow Index: A metric of production flow quality in construction". Construction Management and Economics, v. 37, n. 10, p. 577–580, 2019.
[5] KENLEY, R.; HARFIELD, T. Removing hidden waiting time in critical path schedules: a location-based approach to avoiding waste. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 23., 2015, Perth. Proceedings [...]. Perth: IGLC, 2015. p. 203–210.
[6] GÖRSCH, C.; AL BARAZI, A.; SEPPÄNEN, O.; ABOU IBRAHIM, H. Uncovering and visualizing work process interruptions through quantitative workflow analysis. Lean Construction Journal, 2022, p. 171–183.
[7] RATHNAYAKE, A.; MURGUIA, D.; MIDDLETON, C. Measuring activity level construction productivity. Cambridge: Laing O'Rourke Centre for Construction Engineering and Technology, University of Cambridge, 2024.
[8] HEINECK, L. F. M.; CÂNDIDO, L. F.; LEITE, M. O.; MIRANDA FILHO, A. N. de. Descontinuidade, falta de sequência e variabilidade na produção – ainda estão aí? In: SIMPÓSIO BRASILEIRO DE GESTÃO E ECONOMIA DA CONSTRUÇÃO, 14., 2025, Porto Alegre. Anais [...]. Porto Alegre: ANTAC, 2025.
[9] SACKS, R. What constitutes good production flow in construction? Construction Management and Economics, v. 34, n. 9, p. 641–656, 2016.
[10] KALSAAS, B. T.; BØLVIKEN, T. The flow of work in construction: A conceptual discussion. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 18., 2010, Haifa. Proceedings [...]. Haifa: IGLC, 2010. p. 52–62.
[11] BALLARD, H. G. The last planner system of production control. 2000. Tese (Doutorado) – School of Civil Engineering, Faculty of Engineering, University of Birmingham, Birmingham, 2000.
[12] YIN, R. K. Estudo de caso: planejamento e métodos. 5. ed. Porto Alegre: Bookman, 2015.