Factors generating schedule delays and cost overruns in construction projects

Authors

  • Adriana Gomez-Cabrera <p>Universidad de los Andes</p>
  • Jose Luis Ponz-Tienda <p>Universidad de los Andes</p>
  • Eugenio Pellicer Polytechnic University of Valencia image/svg+xml
  • Amalia Sanz Polytechnic University of Valencia image/svg+xml

DOI:

https://doi.org/10.46421/sibragec.v11i00.39

Keywords:

delays, overruns, construction projects, literature review

Abstract

Delays and cost escalations in construction projects are problems that have been approached by many researchers through time, developing a significant body of literature. This paper developed a literature review to examine 30 research papers published since 1988 in the Web of Science database to identify the main factors causing these deviations. The results show that articles are covering different continents, decades, and project types (infrastructure-building). There are more articles regarding time deviation, and most of the articles belong to Asia and Africa. A list of 73 factors reported in the papers and also the top 10 most common factors. Factors were grouped considering the project life cycle stages, listing those related to Planning/Design (17), and Construction (46) and ten additional factors related to external causes were included.

Downloads

Download data is not yet available.

Published

2021-03-18

Issue

Section

Gestão de Processos Construtivos e Melhoria da Produtividade

How to Cite

GOMEZ-CABRERA, A. et al. Factors generating schedule delays and cost overruns in construction projects. SIMPÓSIO BRASILEIRO DE GESTÃO E ECONOMIA DA CONSTRUÇÃO, v. 11, n. 00, p. 1–10, 18 Mar.2021.

Similar Articles

1-10 of 50

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)