Implementation of the Obeya Room as a Visual Management Tool in Civil Construction: A Case Study of a Vertical Development in Ribeirão Preto (SP)

Authors

DOI:

https://doi.org/10.46421/entac.v21i1.8372

Keywords:

Obeya Room, visual management, Lean Construction, construction planning, construction industry

Abstract

The article analyzes the implementation of the Obeya Room as a visual management tool in civil construction, based on a case study of a vertical housing development in Ribeirão Preto. Using a qualitative-descriptive approach, it evaluates the effects of information centralization, transparency, and interdisciplinary collaboration on project performance. The results indicate significant gains, with a two-month advance in the deadline and a 1.53% cost reduction compared to the initial budget. Specifically considering indirect costs, a more substantial reduction of approximately 9.58% is observed. Improved communication between teams, greater predictability, and better strategic alignment were also noted. It concludes that the Obeya Room has high potential when integrated into a systemic approach based on Lean principles.

Author Biographies

  • Francisco José Riul, Centro Universitário Moura Lacerda

    Postgraduate in Planning, Management, and Control of Civil Works from the Federal University of Rio de Janeiro (Rio de Janeiro - RJ, Brazil).

  • Matheus Almeida Miranda Silva, University of Ribeirão Preto

    Master’s in Environmental Technology from the University of Ribeirão Preto (Ribeirão Preto - SP, Brazil).

References

INTERNATIONAL GROUP FOR LEAN CONSTRUCTION. Proceedings of the International Group for Lean Construction. Disponível em: http://www.iglc.net. Acesso em: 7 abril 2026.

KOSKELA, L. Application of the new production philosophy to construction. Stanford: Stanford University, 1992.

LEAN INSTITUTE BRASIL. Lean Construction e gestão visual. Disponível em: https://www.lean.org.br. Acesso em: 7 abril 2026.

LIKER, J. The Toyota Way. New York: McGraw-Hill, 2004.

LIMMER, C. V. (1997). Planejamento, orçamentação e controle de projetos e obras. Rio de Janeiro: LTC.

OLIVEIRA, I. M. da S. Implementação de ações de melhoria contínua: a gestão visual na melhoria da gestão de desempenho na logística não-alimentar Sonae MC. 2021.

TEZEL, A.; KOSKELA, L.; TZORTZOPOULOS, P. Visual management in construction: study report. Salford: University of Salford, 2009.

TZORTZOPOULOS, P. et al. Design management in construction projects. São Paulo: International Group for Lean Construction, 2006.

Published

2026-09-23

How to Cite

RIUL, F. J.; SILVA, M. A. M. Implementation of the Obeya Room as a Visual Management Tool in Civil Construction: A Case Study of a Vertical Development in Ribeirão Preto (SP). NATIONAL MEETING OF BUILT ENVIRONMENT TECHNOLOGY, v. 21, n. 1, 23 Sept.2026.

Similar Articles

1-10 of 50

You may also start an advanced similarity search for this article.