Population means and sample means in productivity studies
DOI:
https://doi.org/10.46421/entac.v21i1.8964Keywords:
Productivity, Variability, Standard deviation, Sample means, Population meansAbstract
Productivity studies in the construction industry have a long tradition and an extensive body of literature. The use of productivity indicators to support operational decision-making and benchmarking across companies, however, implicitly assumes that the underlying distribution is sufficiently stable for a sample to represent future performance. This assumption has been questioned by several studies due to the high variability inherent in construction processes. Thus, this study aimed to analyze the potential positioning of population means based on sample means in productivity studies. The study adopts a descriptive approach based on literature surveys and field data obtained from four secondary data sources. The study describes ranges of variation observed in sample-based studies and identifies value intervals within which population means may lie for eight construction activities. The findings indicate the existence of wide value spectra in which both sample and population means are distributed, making it difficult to determine with precision the population represented by a given sample. This uncertainty directly affects estimates of productive performance, particularly over short-term periods such as daily or weekly assessments. Finally, the paper suggests mechanisms for future research on the measurement of labor consumption in construction activities.
References
[1] MARCHIORI, F. F., et al., et al. Encontrando um elo perdido: estudos em produtividade na construção civil entre os anos 1940 e 1970 e novos estudos no contexto da indústria 4.0. In: SIMPÓSIO BRASILEIRO DE GESTÃO E ECONOMIA DA CONSTRUÇÃO (SIBRAGEC), 2025. Anais [...] Porto Alegre: ANTAC, 2025.
[2] BISHOP, D., The Background to Management Studies by BRS, Building Research Establishment, Current Paper n. 60/68, Garston, Watford, UK, 1968;
[3] BEAMISH, N., Statistical Analysis of Productivity in the Construction Industry, Building Research Establishment, Internal Note n. 13/78, Garston, Watford, UK, January 1978;
[4] THOMAS, H. R.; YIAKOUMIS, I. Factor Model of Construction Productivity. Journal of Construction Engineering and Management, v. 113, n. 4, p. 623–639, 1987.
[5] SOARES, G. N. Proposição de um Modelo de Gestão da Produtividade e Retroalimentação Orçamentária. 2016. 146 f. Dissertação (Mestrado em Engenharia Civil) – Programa de Pós-Graduação em Engenharia Civil, Universidade Federal do Ceará, Fortaleza, 2016.
[6] SOUZA, U. E. L., Como aumentar a Eficiência da Mão de Obra. São Paulo: PINI, 2006.
[7] BEESTON, D., Statistical Methods for Building Price Data. London: Spon Press, 1983,
[8] HOPP, W.; SPEARMAN, M. L., Factory Physics. New Yorl: Irwin/McGraw-Hill, 1996;
[9] MACCRIMMON, K. R.; RAYVEC, C. A.. A historical note on PERT times. Omega: International Journal of Management Science, v. 17, n. 2, p. 195–200, 1989.
[10] BACK, E., et al., Historical cost data. Journal of Construction Engineering and Management, v. 126, n. 1, p. 29–37, jan./fev. 2000.
[11] FENTE, J.; SCHEXNAYDER, C.; KNUTSON, K., Defining a probability distribution function for construction simulation. Journal of Construction Engineering and Management, v. 126, n. 3, p. 234–241, maio/jun. 2000.
[12] SCHEXNAYDER, C., KNUTSON, K., Fente, J., Describing a beta probability distribution function for construction simulation. Journal of Construction Engineering and Management, v. 131, n. 2, p. 221–229, fev. 2005.
[13] GRAHAM, L. D., SMITH, S. D., DUNLOP, P., Lognormal distribution provides an optimum representation of the concrete delivery placement process. Journal of Construction Engineering and Management, v. 131, n. 2, p. 230–238, fev. 2005.
[14] CHAU, K. W. The validity of the triangular distribution assumption in Monte Carlo simulation of construction costs: empirical evidence from Hong Kong. Construction Management and Economics, v. 13, p. 15–21, 1995
[15] CHAU, K. W., Monte Carlo simulation of construction cost using subjective data, Construction Management and Economics. and Econ., vol. 13, 1995, p. 369-383;
[16] FELLOWS, R., Note: Monte Carlo simulation of construction costs using subjective data: comment. Construction Management and Economics, v. 14, p. 457–460, 1996.
[17] Ballard, G., et al. Discussion of “improving labor flow reliability for better productivity as lean construction principle, Journal of Construction Engineering and Management, may 2005.
[18] THOMAS, H. R. et al. Improving labor flow reliability for better productivity as lean construction principle, Journal of Construction Engineering and Management, v. 129, n. 3, p. 251–261, maio/jun. 2003.
[19] BASHFORD, H. H.; WALSH K. D.; SAWHNEY, A. Production system loading – cycle time relationship in residential construction, Journal of Construction Engineering and Management, v. 131, n. 1, p. 15–22, jan. 2005.
[20] WALSH, K. D.; SAWHNEY, A.; BASHFORD, H. H. Production equations for unsteady-state construction processes, Journal of Construction Engineering and Management, v. 133, n. 3, p. 254–261, mar. 2007.
[21] RADOSAVLJEVIC, M., HORNER, R. M., The evidence of complex variability in construction labour productivity, Construction Management and Economics, v. 20, p. 3–12, 2002.
[22] PANZETER, A. A., Estudo das relações entre os consumos de mão de obra e as quantidades físicas executadas.1998. Dissertação (Mestrado em Engenharia Civil) – Programa de Pós-Graduação em Engenharia Civil, Universidade Federal do Rio Grande do Sul, Porto Alegre, 1988.
[23] OTERO, J. A., Análise Paramétrica de Dados Orçamentários para Estimativa de Custos na Construção de Edifícios – estudo de caso voltado para a questão da variabilidade, 2000. Dissertação (Mestrado em Engenharia de Produção) – Universidade Federal de Santa Catarina, Florianópolis, mar. 2000.
[24] VIEIRA, J. C.; PUHL FILHO, O., Variabilidade na produção em serviços da construção civil: análise da produção de uma firma de estaqueamento In: ENCONTRO NACIONAL DE ENGENHARIA DE PRODUÇÃO (ENEGEP), 9., 1989, Porto Alegre. Anais [...]. Porto Alegre: UFRGS, 1989.
[25] SOARES, J. C. Variabilidade nos resultados da medição de produtividade das alvenarias e em reboco de uma empresa de construção civil. In: ENCONTRO NACIONAL DE ENGENHARIA DE PRODUÇÃO (ENEGEP), 14., 1994, João Pessoa. Anais [...]. João Pessoa, out. 1994.;
[26] CAIXA ECONÔMICA FEDERAL, Sinapi, Sistema Nacional de Pesquisa de Custos e Índices da Construção Civil, Tabelas atualizadas 2026;
[27] AMBROZEWICZ, P. H. L. SIQ-C: metodologia de implantação: procedimentos, serviços e materiais. Curitiba: Serviço Nacional de Aprendizagem Industrial. Departamento Regional Paraná, 2003. 732p.