Apartment customization and its influence on construction planning: a case study in a high-end residential building

Authors

  • Vitor Gazaro Martello Federal University of Rio Grande do Sul image/svg+xml
  • Guilherme Luiz Canzian Marion Federal University of Rio Grande do Sul image/svg+xml
  • Lais Zucchetti Federal University of Rio Grande do Sul image/svg+xml

DOI:

https://doi.org/10.46421/entac.v21i1.8958

Keywords:

Personalização, Planejamento, Desvio de prazo, Construção civil, Lean Construction

Abstract

Apartment customization has been adopted as a value-adding strategy in the real estate market, especially in high-end developments. However, this practice introduces variability into the production system, potentially compromising planning and production control. This study quantitatively analyzes the impacts of late customization on the construction schedule of a residential building. A case study was conducted based on the comparison between baseline planning and actual execution, using schedule deviation as the main metric. Electrical, hydraulic, HVAC, and drywall systems were analyzed. The results indicate a cumulative deviation of 14.12% in physical progress and delays exceeding 100 days in installation activities. It is concluded that late customization shifts the Customer Order Decoupling Point, compromising workflow.

Published

2026-09-05

How to Cite

MARTELLO, V. G.; CANZIAN MARION, G. L.; ZUCCHETTI, L. Apartment customization and its influence on construction planning: a case study in a high-end residential building. NATIONAL MEETING OF BUILT ENVIRONMENT TECHNOLOGY, v. 21, n. 1, 5 Sept.2026.