Analysis of the PPC indicator in a vertical residential building with focus on the unit customization phase
DOI:
https://doi.org/10.46421/entac.v21i1.8891Keywords:
PPC, Customization, Construction planning, Construction production controlAbstract
This article analyzes the performance of short-term planning in a high-rise residential building located in São Paulo, with over 30 floors. The study focused on the final stages of the construction process, during which unit customization services were carried out, such as the installation of countertops, wall coverings, sinks, and faucets. Over a five-week period, the Percent Plan Complete (PPC), the main planning reliability metric of the Last Planner System, was monitored to evaluate performance and identify bottlenecks. The results show that, for most of the study period, the PPC remained below the average of 78%, reflecting challenges such as scheduling failures, material delivery delays, and difficulties in mobilizing external suppliers. The analysis of Reasons for Non-Compliance (RNC) concludes that structuring customization phases in the medium-term schedule and systematically monitoring PPC supports the implementation of structural improvements based on the identified root causes.
References
[1] DANIEL, E. I. et al. The history of the development of the Last Planner System. Lean Construction Blog, 2017. Disponível em: leanconstructionblog.com. Acesso em: abr. 2026.
[2] BALLARD, H. G. The Last Planner System of Production Control. 2000. 272 f. Tese (Doutorado em Engenharia Civil) - School of Civil Engineering, The University of Birmingham, Birmingham, 2000.
[3] KOSKELA, L. Management of production in construction: a theoretical view. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 7., 1999, Berkeley. Proceedings [...] Berkeley: IGLC, 1999. p. 241-252.
[4] BALLARD, G.; TOMMELEIN, I. Current Process Benchmark for the Last Planner System. Berkeley: Project Production Systems Laboratory, P2SL, University of California, 2016. Disponível em: p2sl.berkeley.edu.
[5] BALLARD, G.; HOWELL, G. An update on Last Planner. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 11., 2003, Blacksburg. Proceedings [...] Blacksburg: IGLC, 2003.
[6] NAHMENS, I.; MULLENS, M. A. Mass customization in homebuilding: is there a relationship between product variety and lean production? International Journal of Construction Education and Research, v. 5, n. 4, p. 257-275, 2009.
[7] ALSEHAIMI, A.; KOSKELA, L. Inadequate project management as a reason for delay in construction: a literature review. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 16., 2008, Manchester. Proceedings [...] Manchester: IGLC, 2008.
[8] EZZAT, H. A. et al. Investigating the application of one piece flow from lean manufacturing in the construction delivery of mass housing projects. PLoS ONE, v. 20, n. 5, 2025. DOI: 10.1371/journal.pone.0320398.
[9] KOSKELA, L. Application of the New Production Philosophy to Construction. Technical Report No. 72. Stanford: Center for Integrated Facility Engineering, Stanford University, 1992.
[10] HAMZEH, F.; BALLARD, G.; TOMMELEIN, I. D. Rethinking lookahead planning to optimize construction workflow. Lean Construction Journal, p. 15-34, 2012.
[11] HAMZEH, F. R. Improving Construction Workflow: The Role of Production Planning and Control. 2009. Tese (Doutorado) - University of California, Berkeley, 2009.
[12] TSAO, C. C. Y. et al. 5 levels of the Last Planner System: "Should, Can, Will, Did and Learn". Lean Construction Blog, 2014. Disponível em: leanconstructionblog.com. Acesso em: abr. 2026.
[13] FIALLO, M. C.; REVELO, V. H. Applying the Last Planner control system to a construction project: a case study in Quito, Ecuador. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 10., 2002, Gramado. Proceedings [...] Gramado: IGLC, 2002. p. 1-11.
[14] ZANDY, K. Root cause analysis: 3 must-dos after scoring Percent Plan Complete. The Lean Builder, 2023. Disponível em: theleanbuilder.com. Acesso em: abr. 2026.
[15] GONZALEZ, V. et al. Using Percent Plan Complete for early success assessment in the Last Planner System. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 22., 2014, Oslo. Proceedings [...] Oslo: IGLC, 2014.
[16] ROCHA, C. G. da. A conceptual framework for defining customisation strategies in the house-building sector. 2011. Tese (Doutorado em Engenharia Civil) - Universidade Federal do Rio Grande do Sul, Porto Alegre, 2011.
[17] ROCHA, C. G.; KEMMER, S. Method to implement delayed product differentiation in construction of high-rise apartment building projects. Journal of Construction Engineering and Management, v. 140, n. 6, 2014. DOI: 10.1061/(ASCE)CO.1943-7862.0000758.
[18] ASLAM, M. et al. Exploring factors for implementing lean construction for rapid initial successes in construction. Journal of Cleaner Production, v. 277, p. 123295, 2020. DOI: 10.1016/j.jclepro.2020.123295.
[19] SINGH, A. et al. Implementation of lean construction to reduce rework in construction projects: a systematic literature review. In: Lecture Notes in Civil Engineering, v. 282. Singapore: Springer, 2023. DOI: 10.1007/978-981-99-5455-1_18.
[20] YIN, R. K. Estudo de caso: planejamento e métodos. 5. ed. Porto Alegre: Bookman, 2015.