CAUSAS DE ATRASOS EM OBRAS DE EDIFICAÇÕES PÚBLICAS: LEVANTAMENTO DE PUBLICAÇÕES NO PERÍODO 2009-2020

Authors

  • Amanda Aparecida Souza Faculdade de Engenharia Civil (FECIV-UFU)
  • Dogmar Antônio de Souza Junior Faculdade de Engenharia Civil (FECIV-UFU)
  • Eliane Betânia Carvalho Costa Faculdade de Engenharia Civil (FECIV-UFU)

DOI:

https://doi.org/10.46421/entac.v18i.1051

Keywords:

Delay, Public projects, Building, Schedule, Management

Abstract

Construction delay is a commom problem in building construction leading to litigation and disputes between those involved. Public projects that are paralyzed and/or unfinished carry debts to the govern compromising public resources that could be used for benefit of society. The purpose of this study was to do a survey on the research related to delay in public building from 2009 to 2020. The adopted method consisted in the publications analysis on database research using keywords. Eleven studies were evaluated, eight international and three Brazilian. The results obtained showed that the most frequent causes of delays in public building works are changes in the project scope, weather conditions and related to poor management of layout site construction.

References

AHMAD, H.; AYOUSH, M.; AL-ALWAN, M.; Causes of delay to public infrastructure projects according to engineers representing different contract parties. Built Environment Project and Asset Management, v. 10, n. 1, p. 153-179, 2020.

AL-MOMANI, H. A. Construction delay: a quantitative analysis. International Journal of Project Management, v. 18, n. 1, p. 51-59, 2000.

ALVARENGA, F. C. Análise das causas de aditivos de custo e prazo em obras públicas de instituições federais de ensino. Dissertação (Mestrado) – Instituto de Tecnologia, Universidade Federal do Pará, Belém, 2019.

ALZARA, M.; KASHIWAGI, J.; KASHIWAGI, D.; AL-TASSAN, A. Using PIPS to minimize causes of delay in Saudi Arabian construction projects: university case study. Procedia Engineering, v. 145, p. 932 – 939, 2016.

APOLOT, R.; ALINAITWE, H.; TINDIWENSI, D. An investigation into the causes of delay and cost overrun in Uganda’s public sector construction projects. Journal of Construction in Developing Countries, v. 18, n. 2, p. 33–47, 2013.

ASSAF. S. A.; AL-HEJJI, S. Causes of delay in Large Construction Projects. International Journal of Project Management, v. 24. n. 04. p. 349-357. 2006.

BAGAYA, O.; SONG, J. Empirical study of factors influencing schedule delays of public construction projects in Burkina Faso. J. Manage. Eng., v. 32, n. 5, 2016.

BRANDSTETTER, M. C. G. O.; RIBEIRO, H. R. O. Causas de custos adicionais e impacto financeiro em obras públicas sob a perspectiva da gestão de risco. Ambiente construído, v. 20, n. 1, 2020.

BRASIL. Lei de Licitação nº 8666, de 21 de junho de 1993.

BELTRÃO, L. M. P.; CARVALHO, M. T. M. Prioritizing construction risks using fuzzy AHP in Brazilian Public Enterprises. J. Constr. Eng. Manage, v. 145, n. 2, 2019.

COLPO, I.; WEISE, A. D.; MEDEIROS, F. S. B.; LOBLER, M. L. Atrasos na execução de obras públicas: Estudo em uma instituição federal de ensino superior. Revista Produção Online, v. 18, n. 4, p. 1322-1343, 2018.

CONFEDERAÇÃO NACIONAL DA INDÚSTRIA. A infraestrutura no Brasil. Rio de Janeiro. 2018.

Disponível em: http://www.portaldaindustria.com.br/cni/canais/infraestrutura/. Acesso em: 06 mar. 2018.

DAS, D. K.; EMUZE, F. A dynamic model of contractor-induced delays in India. Journal of Construction in Developing Countries, v. 22, n. 1, p. 21–39, 2017.

FAMIYEH, S.; AMOATEY, C. T.; ADAKU, E.; AGBENOHEVI, C. S. Major causes of construction time and cost overruns: A case of selected educational sector projects in Ghana. Journal of Engineering, Design and Technology, v. 15, n. 2, p. 181-198, 2017.

FREITAS, L. A.; CARVALHO, M. T. M. Levantamento de aumento do custo e do prazo de obras públicas de 2008 a 2015. In: Simpósio Brasileiro de Tecnologia da Informação e Comunicação na Construção, 1.,/Simpósio Brasileiro de Gestão e Economia da Construção, 10., 2017, Fortaleza. Anais... Porto Alegre: ANTAC,2016.

GEBREHIWET, T.; LUO, H. Analysis of delay impact on construction project based on RII and correlation coefficient: Empirical study. Procedia Engineering, v. 196, p. 366-374, 2017.

GUIDI, J. E. O labirinto das obras públicas. Brasília: Câmara Brasileira da Indústria da Construção, 2020.

HASEEB, M.; LU, X.; BIBI, A.; DYAN, M; RABBANI, W. Problems of projects and effects of delays in the construction industry of Pakistan. Australian Journal of Business and Management Research, v. 1, n. 5, p. 41-50, 2011.

MAUÊS, L. M. F.; SANTANA, W. B.; SANTOS, P. C.; NEVES, R. M.; DUARTE, A. A. Construction delays: a case study in the Brazilian Amazon. Ambiente construído, v. 17, n. 3, p. 167-181, 2017.

MBALA, M.; AIGBAVBOA, C.; ALIU, J. Causes of delay in various construction projects: A literature review. In: In: Charytonowicz J., Falcão C. (eds) Advances in Human Factors, Sustainable Urban Planning and Infrastructure. AHFE 2018. Advances in Intelligent Systems and Computing, v. 788. Springer, 2018.

MUIANGA, E. A. D.; GRANJA, A. D.; RUIZ, J. A. Desvios de custos e prazos em empreendimentos da construção civil: categorização e fatores de influência. Ambiente construído, v. 15, n. 1, p. 79-97, 2015.

RACHID, Z.; TOUFIK, B.; MOHAMMED, B. Causes of schedule delays in construction projects in Algeria. International Journal of Construction Management, v. 19, n.5, p. 371-381, 2019.

RAMLI, et al. Influence of project type, location and area towards construction delay: a review on significance level of delay factors. International Journal of Engineering & Technology, v. 7, n. 4, p. 392-399, 2018.

REIS, C. J. L; SEIXAS, R.M; SILVA, G. B; MAUÉS, L.M.F; DUARTE, A. M. Identificação das causas de atrasos de obras: um estudo de caso na região metropolitana de Belém. In: XVI ENCONTRO NACIONAL DE TECNOLOGIA DO AMBIENTE CONSTRUÍDO, 16., 2016, São Paulo. Anais... Porto Alegre: ANTAC,2016.

SANNI-ANIBIRE, M. O.; ZIN, R. M.; OLATUNJI, S. O. Causes of delay in the global construction industry: A meta analytical review. International Journal of Construction Management, 2020.

SANTOS, H. P.; STARLING, C. M. D.; ANDERY, P. R. P. Um estudo sobre as causas de aumentos de custos e prazos em obras de edificações públicas municipais. Ambiente construído, v. 15, n. 4, p. 225-242, 2015.

ZIDANE, Y. J. T.; ANDERSEN, B. The top 10 universal delay factors in construction projects.

International Journal of Managing Projects in Business, v. 11, n. 3, p. 650-672, 2018.

Published

2020-11-04

How to Cite

SOUZA, Amanda Aparecida; SOUZA JUNIOR, Dogmar Antônio de; COSTA, Eliane Betânia Carvalho. CAUSAS DE ATRASOS EM OBRAS DE EDIFICAÇÕES PÚBLICAS: LEVANTAMENTO DE PUBLICAÇÕES NO PERÍODO 2009-2020. In: NATIONAL MEETING OF BUILT ENVIRONMENT TECHNOLOGY, 18., 2020. Anais [...]. Porto Alegre: ANTAC, 2020. p. 1–9. DOI: 10.46421/entac.v18i.1051. Disponível em: https://eventos.antac.org.br/index.php/entac/article/view/1051. Acesso em: 18 jul. 2024.