ANÁLISE DOS BENEFÍCIOS DO 4D BUILDING INFORMATION MODELING (BIM) NA ATUALIZAÇÃO E CONTROLE DO CRONOGRAMA DE OBRAS RODOVIÁRIAS

Authors

  • Thalyta de Miranda Lanna Rios Escola Politécnica da Universidade de São Paulo
  • Tiely Zurlo Mognhol Escola Politécnica da Universidade de São Paulo
  • Luiz Reynaldo de Azevedo Cardoso Escola Politécnica da Universidade de São Paulo

DOI:

https://doi.org/10.46421/entac.v18i.1199

Keywords:

4D BIM, Time management, Highways, Schedule, Control

Abstract

It is worth to highlight that the processes used to updated and control the schedule of road works in Brazil are, in many cases, based on forms with manual record, demanding more time to identify possible deviations, as well as attributing answers to these. In this context, the objective of this study is to evaluate how 4D BIM may contribute to optimize the update and schedule control of road works, integrating different technologies in processes of time management. The research methodology is based on: a literature review, presenting the scenario of time management in road works and the possible contributions of the 4D BIM for optimizing the mentioned processes; and a case study contextualizing the process adopted for managing time in a road work. As a result, it is intended to establish a parallel between literature and the practices of time management in road works, and to highlight the possible benefits of using the 4D BIM and associated technologies, such as unmanned aerial vehicles (UAVs), laser scanners, tablets among others.

References

BORGES, M. L. A. E. Método para a implementação da modelagem BIM 4D em empresas construtoras. Dissertação (Mestrado) - Universidade Federal do Rio Grande do Norte, Centro de Tecnologia, Programa de Pós-Graduação em Engenharia Civil, Natal, 2019.

CARVALHO, M. M. G. Gestão de projetos: o BIM nas organizações. Dissertação (mestrado).

Instituto Superior de Engenharia do Porto, Porto, 2016.

CORREA, S. L. M. et al. BIM para infraestrutura de transportes. In: Simpósio Brasileiro de Tecnologia da Informação e Comunicação na Construção, 2., 2019, Campinas, SP. Anais [...]. Porto Alegre: ANTAC, 2019. Disponível em:https://antaceventos.net.br/index.php/sbtic/sbtic2019/paper/view/180COSTIN, A. Building Information Modeling (BIM) for transportation infrastructure: Literature review, applications, challenges and recommendations. Automation in Construction, Elsevier, 2018.

DODGE DATA AND ANALYTICS. The business value of BIM for infrastructure 2017. SmartMarket Report, v. 1, n. 2017, p. 1–68, 27 set. 2017.

HAMLEDARI, H. et al. (2017a). Automated schedule and progress updating of IFC-Based 4D BIMs. Journal of Computing in Civil Engineering, 31(4), 1–16.

HAMLEDARI, H. et al. (2017b). Evaluation of computer vision- And 4D BIM-based construction progress tracking on a UAV platform. 6th CSCE-CRC International Construction Specialty Conference 2017 - Held as Part of the Canadian Society for Civil Engineering Annual Conference and General Meeting 2017, 1(March), 621–630.

KIM, H. et al. Developing a 3D intelligent object model for the application of construction planning/simulation in a highway project. KSCE J Civ Eng 20, 538–548 (2016) doi:10.1007/s12205-015-0463-4LIN J.J.; GOLPARVAR-FARD M. (2018) Visual data and predictive analytics for proactive project controls on construction sites. In: Smith I., Domer B. (eds) Advanced Computing Strategies for Engineering. EG-ICE 2018. Lecture Notes in Computer Science, vol 10863. Springer, Cham.

MATTOS, Al. D. Planejamento e controle de obras. São Paulo: Pini, 2014.

MAWLANA, M.; VAHDATIKHAKI, F.; DORIANI, A.; HAMMAD, A. Integrating 4D modeling and discrete event simulation for phasing evaluation of elevated urban highway reconstruction projects. Automation in Construction, 2015.

NARCISO, M. A. Gerenciamento do tempo do projeto aplicado a obras civis: como diminuir os problemas com atraso, custo e qualidade. Brasília – DF: UNICEUB, 2013. 30 p.

OH, M.; HONG, S.; LEE, J.; JEONG, Y. Integrated system for BIM-based collaborative design.

Automation In Construction, v. 58, p.196-206, out. 2015. Elsevier BV.

PARK, J.; CAI H. (2017) Framework of dynamic Daily 4D BIM for tracking construction progress through a web environment. Congress on Computing in Civil Engineering, Proceedings. pp.

193-201SILVA, M. A. O.; CORRÊA, L. R.; RUAS, A. X. A. Gerenciamento de projetos na construção civil: tempo, custo e qualidade. Revista Construindo, Belo Horizonte. Volume 10, número 02, p. 01 –20, Jul - Dez. 2018.

SILVA, M. V. B. Gestão do tempo na construção civil e sua relação com as demais áreas da gestão de projetos. Revista Especialize On-line IPOG - Goiânia - 9ª Edição nº 010 Vol.01/2015 julho/2015TIRUNAGARI, H. V.; KONE, V. (2019). Simulation of construction sequence using BIM 4D techniques. International Journal of Recent Technology and Engineering, 7(6), 877–881.

TSAI, M. H. et al. (2019). Experiences using building information modeling for a construction project. EG-ICE 2010 - 17th International Workshop on Intelligent Computing in Engineering, (July).

VILVENTHAN, A.; RAJADURAI, R. (2019). 4D Bridge Information Modelling for management of bridge projects: a case study from India. Built Environment Project and Asset Management. https://doi.org/10.1108/BEPAM-05-2019-0045YIN, R. K. Case study research: design and methods. Newbury Park: Rev. ed. Sage Publications, 1991.

Published

2020-11-04

How to Cite

RIOS, Thalyta de Miranda Lanna; MOGNHOL, Tiely Zurlo; CARDOSO, Luiz Reynaldo de Azevedo. ANÁLISE DOS BENEFÍCIOS DO 4D BUILDING INFORMATION MODELING (BIM) NA ATUALIZAÇÃO E CONTROLE DO CRONOGRAMA DE OBRAS RODOVIÁRIAS. In: NATIONAL MEETING OF BUILT ENVIRONMENT TECHNOLOGY, 18., 2020. Anais [...]. Porto Alegre: ANTAC, 2020. p. 1–9. DOI: 10.46421/entac.v18i.1199. Disponível em: https://eventos.antac.org.br/index.php/entac/article/view/1199. Acesso em: 25 nov. 2024.

Issue

Section

(Inativa) Tecnologia da Informação e Comunicação

Similar Articles

<< < 35 36 37 38 39 40 41 42 43 44 > >> 

You may also start an advanced similarity search for this article.