Development of a framework using 4D BIM tools applied to the planning of social housing projects
DOI:
https://doi.org/10.46421/entac.v20i1.6045Keywords:
Planning, BIM, 4D modeling, Social housing, FrameworkAbstract
Brazil has a large housing deficit. A significant portion of the activities related to reducing this deficit come from the construction industry. However, this same sector is affected by inconsistent information that lacks the necessary level of detail and which affects the planning and control stage of construction work. Thus, the use of new tools has been proposed to change the current state of this sector, such as Building Information Modeling - BIM. This research aimed to develop a framework for adopting BIM as a tool to support 4D planning in a case study of a social housing project. A literature review was carried out on the main concepts and applications of 4D BIM use for BIM planning, followed by the development of a framework to be applied in a case study of social housing projects. As a result, it was found that the framework for planning with 4D BIM can be applied to the pre-construction phases by carrying out project simulation and, in the execution phase, it can offer a visualization of the project's progress by comparing the real scenario with the scenario planned through 4D simulation. Among the main benefits perceived in this study through the use of 4D BIM models as a planning support tool was the possibility of detailed visualization, which acts as an innovative solution to overcome the shortcomings of current planning practices.
References
BIOTTO, C. FORMOSO, C.; ISATTO, E. Uso de modelagem 4D e Building Information Modeling na gestão de sistemas de produção
em empreendimentos de construção. Ambiente Construído, v. 15, p. 79-96, 2015.
MARTINS, S. et al. Evaluation of 4D BIM tools applicability in construction planning efficiency. InternationalJournal of Construction
Management, v.22,n. 15, p. 2987-3000, 2022.
BRITO, D.; FERREIRA, E. Evaluation of strategies for representation and analysis of construction planning and control using 4D BIM
models. Ambiente Construído, v. 15, p. 203-223, 2015.
CROWTHER, J.; AJAYI, S. Impact Of 4D BIM on construction project performance.International Journal of Construction
Management, v.21, n.7, p. 724-737, 2021
LAUFER, A. et al.President preconstruction planning process. Journal Of construction engineering and
management,v.119,n.3,p.426-444, 1993.
SILVA, P. CRIPPA, J. SCHEER, S. BIM 4D no planejamento de obras: detalhamento, benefícios e dificuldades. PARC Pesquisa em
Arquitetura e Construção, Campinas, SP,v.10, p.e 019010,feb.2019.ISSN 1980-6809. Disponível em:
periodicos.sbu.unicamp.br/ojs/index.php/parc/article/view/8650258>. Acesso em: 18 junho de 2023.
CIC-COMPUTER INTEGRATED CONSTRUCTION Research Program. BIM Project Execution Planning Guide.Version 2.1,The
Pennsylvania State University, University Park, PA, USA. 2011. Disponível em: <http://bim.psu.edu>. Acesso em:15 de junho de
EASTMAN, C. BIM handbook: A guide to building information modeling for owners, managers,designers,engineers and
contractors.John Wiley & Sons, 2011.
VA- U.S.DEPARTMENT OF VETERANS AFFAIRS. TheVABIMGuide.v.1.0, Washington: VA,2010.
CBIC-CÂMARA BRASILEIRA INDÚSTRIA DA CONSTRUÇÃO. Coletânea Implementação do BIM para construtoras e incorporadoras:
volume 5 formas de contratação BIM. Brasília: CBIC, 2016.
WANG, W. et al. Integrating building information models with construction process simulations for project scheduling support.
Automation in construction, v. 37, p. 68-80, 2014.
ALLEN, C.; SMALLWOOD, J. Improving construction planning through 4D planning. Journal Of Engineering, Design and Technology,
v.6, n.1, p. 7-20, 2008.
MARTINS, S. et al. Evaluation of 4D BIM tools applicability in construction planning efficiency. International Journal of Construction
Management, v. 22, n. 15, p. 2987-3000, 2022.
SLOOT, R.; HEUTINK, A.; VOORDIJK, J. Assessing usefulness of 4D BIM tools in risk mitigation strategies. Automation in
Construction, v. 106, p. 102881, 2019.
CHAHROUR, R. et al. Cost-benefit analysis of BIM-enabled design clash detection and resolution. Construction Management and
Economics, v.39, n.1, p.55-72,2021.
VARGAS, F.FORMOSO, C. Method for location-based production planning and control supported by BIM. Ambiente
Construído,v.20,p.129-151,2020.
KOSKELA, L.; HOWELL, G. The underlying theory of project management is obsolete. In: Proceedings Of the PMI research
conference. PMI,2002. p.293- 302.
RASHIDI, A. et al. Construction planning through 4D BIM-based virtual reality for light steel framing building projects. Smart and
Sustainable Built Environment, v. 12, n. 5, p. 1153-1173, 2023.
GLEDSON, B.; GREENWOOD, D. The adoption of 4D BIM in the UK construction industry: an innovation diffusion approach.
Engineering, Construction and Architectural Management, v. 24, n. 6, p. 950-967, 2017.
CHAREF, R.; ALAKA, H.; EMMITT, S. Beyond the third dimension of BIM: A systematic review of literature and assessment of
professional views. Journal of Building Engineering, v. 19, p. 242-257, 2018.
HOSSEINI, M. et al. Analysis of citation networks in building information modeling research. Journal of Construction Engineering
and Management, v. 144, n. 8, p. 04018064, 2018.
SON,H.;KIM,C.; KWON CHO, Y. Automated schedule up date using as-built data and a 4D building information model. Journal of
Management in Engineering, v. 33, n. 4, p. 04017012, 2017.
KYMMELL, W. Building Information Modeling: planning and managing construction projects with 4D CAD and simulations. New
York: McGraw-Hill, 2008.
MOON, H. et al. BIM-based construction scheduling method using optimization theory for reducing activity overlaps. Journal of
Computing in Civil Engineering, v. 29, n. 3, p. 04014048, 2015.
MA, Hui; ZHANG, Hongbin; CHANG, Peng. 4D-based workspace conflict detection in prefabricated building constructions. Journal
of Construction Engineering and Management, v. 146, n. 9, p. 04020112, 2020.
MIRZAEI, Ali et al. 4D-BIM dynamic time–space conflict detection and quantification system for building construction projects.
Journal of construction engineering and management, v. 144, n. 7, p. 04018056, 2018.
SCHEER, S. et al. On-site BIM model use to integrate 4D/5D activities and construction works: a case study on a Brazilian low
income housing enterprise. In: Computing in Civil and Building Engineering (2014). 2014. p. 455-462.
LI, H. et al. Virtual prototyping for planning bridge construction. Automation in construction, v. 27, p. 1-10, 2012.
SACKS,R. et al. Manual De BIM: Um Guia de Modelagem da informação da Construção Para Arquitetos, Engenheiros, Gerentes,
Construtores e Incorporadores. Bookman Editora, 2021.
ALTOQI. Orçamentação e planejamento de obras em BIM. Disponível em:<https://altoqi.com.br/visus>. Acesso em: 10 de agosto
de 2023.
BAIA, D. Uso de Ferramentas BIM para o Planejamento de Obras da Construção Civil. 2015. 117f. Tese (Mestrado em Engenharia
Civil) - Departamento de Engenharia Civil Ambiental,Universidade de Brasília, Brasília, 2015.
ELGHAISH,F.;ABRISHAMI,S. Developing Framework To revolutionise the4D BIM process: IPD-based solution. Construction
Innovation, v. 20, n. 3, p. 401- 420, 2020.
NAFE ASSAFI,M. et al. Development and validation of a framework for preventing and mitigating construction delay using 4D BIM
platform in Bangladeshi construction sector. Construction Innovation, 2022.
BRITO, D.; FERREIRA, E. Evaluation of strategies for representation and analysis of construction planning and control using 4D BIM
models. Ambiente Construído, v. 15, p. 203-223, 2015.
SON,H.;KIM,C.;KWON CHO, Y. Automated Scheduleupdate Using As-built data and a 4D building information model. Journal of
Management in Engineering, v. 33, n. 4, p. 04017012, 2017.
GIESTA,J. etal. O uso da tecnologia BIM na quantificação e planejamento: estudo de caso de residência RN–Brasil. In: CONGRESSO
PORTUGUÊS DE BUILDING INFORMATION MODELLING. 2018.
SHEIKHKHOSHKAR,M. et al. Automated planning concrete joint layouts with 4D-BIM. Automation in construction, v. 107, p. 102943,
DA MOTA BEZERRA, C.; RIBEIRO, S.. O PLANEJAMENTO E A ESTIMATIVA DE CUSTO NO AMBIENTE DE MODELAGEM BIM: UM
ESTUDO DE CASO. 2020.
MADRUGA, F.;RIBEIRO,S. O BIM aplicado no planejamento em obra de habitação de interesse social: estudo de caso. In: congresso
português de building information modelling. 2020. p. 941-950.
DODDS, Jason; JOHNSON, Scott. Mastering autodesk navisworks 2013. John Wiley & Sons, 2012.
RITZ,G..;LEVY,S. Total Construction Project Management. NewYork,NY: McGraw-Hill, 1994.
SOLOMON, P. (2005), “The essence of good planning – putting planning into context”. Disponivel em:
.Acesso em: 6 de junho de 2023
KERZNER,H. Project Management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons, 2017.