THE USE OF 4D AND 5D METHODOLOGY FOR WORKS MANAGEMENT AND PLANNING: SYSTEMATIC LITERATURE REVIEW

Authors

  • Nathalia Carneiro Universidade Federal de Uberlândia-PPGAU
  • Ana Carolina Maciel Universidade Federal de Uberlândia-FECIV
  • Carolina Vaz Universidade Federal de Uberlândia- PPGAU
  • André Luís de Araujo Universidade Federal de Uberlândia - PPGAU

DOI:

https://doi.org/10.29327/sbqp2021.438152

Keywords:

BIM 4D, BIM 5D, Construction management, Construction planning

Abstract

The global production dynamics, after globalization, is rapidly changing. As a result, this came the need to discuss new demands for organization and planning within civil construction involving new techniques and Technologies that meet the need to produce sustainable and quality products. In search of new concepts to expand studies of solution that improve the dynamics of construction management, this article through a systematic review of the literature, aimed to provide diversity and complexity of studies produced on the theme of construction management using Building Information Modeling (BIM). This paper aims to explore an overview about construction management related to BIM 4D and BIM 5D in Architecture, Engineering and Construction (AEC). Among the challenging topics most addressed in the work carried out with the theme is the lack of expertise and training of professionals who understand the methodology within the area of construction management, fostering the need to expand discussions on the subject.

References

ACHKAR, Esper. A BIM-integrated approach to construction quality management enablinginformation and knowledge management during the execution phase of a project life cycle.

2016. 80 p. Dissertação. Master of Construction Management and Engineering, EindhovenUniversity of Technology, Eindhoven, Países Baixos, 2016.

ALADAG, Hande; DEMIRDÖGEN, Gökhan; ISIK, Zeynep. Building Information Modeling (BIM)Use in Turkish Construction Industry. Procedia Engineering, [S. l.], v. 161, p. 174-179, 5 ago.

2016. DOI https://doi.org/10.1016/j.proeng.2016.08.520.

ÁLVARES, J.; COSTA, D.; Barbosa, A. Proposta de método para monitoramento visualsistemático do progresso de obras baseado em mapeamentos 3D por Vant e BIM 4D. RevistaTécnico-científica do CREA-PR, [s. l.], ed. Ed. Especial XVII, p. 312-325, 12 nov. 2018. Disponívelem: http://creaprw16.crea-pr.org.br/revista/Sistema/index.php/revista/article/view/507.Acesso em: 12 out. 2020.

ARAÚJO, J.; LINO, J.; COUTO, P. Ferramentas BIM de apoio à gestão de obra. In: 1º CongressoPortuguês de Building Information Modelling, Braga, Portugal, ed. 1ª, nov. 2016. AnaisEletrônicos[...]. Braga: ptBIM, 2016, p. 1-13, 24. Disponível em:https://www.researchgate.net/publication/311845064_FERRAMENTAS_BIM_DE_APOIO_A_GESTAO_DE_OBRA. Acesso em: 05 de jun. de 2021.

BALLARD, G. Look ahead Planning: the missing link in production control.In: Annualconference of the international group for lean construction, Gold Coast, 1997.

Proceedings[...]. Gold Coast: IGLC, 1997.

BULGAKOV, A.; BOCK, T. Integration of Lean Management Methods in Construction and theBuilding Information Modelling. In: MATEC Web of Conferences. Proceedings[...]. MATEC,2018, v. 251, n. 7, 14 dez. 2018. DOI https://doi.org/10.1051/matecconf/201825105040.

BALAKINA, A.; SIMANKINA; Tatyana; LUKINOV, Vitaly. 4D modeling in high-rise construction. In:E3S Web of Conferences. Proceedings[...]. E3S Web Conf., High-Rise Construction 2017 (HRC2017), ano 1, v. 33, n. 03044, 6 mar. 2018. 3 Construction Technology and Management, p. 1-5. DOI: https://doi.org/10.1051/e3sconf/20183303044.

BOMFIM, C.; LISBOA, B.; MATOS; P. Gestão de Obras com BIM – Uma nova era para o setorda Construção Civil. In: SIGraDi 2016. Anais eletrônicos[...]. XX Congress of the IberoamericanSociety of Digital Graphics, Buenos Aires, Argentina, p. 556-560, 9 nov. 2016. DOI10.5151/despro-sigradi2016-724.

COELHO, D. Utilização do BIM 4D e 5D enquanto metodologia avançada para oplaneamento, preparação e monitorização de obras. 2016. 148 p. Dissertação (Grau deMestre em Engenharia Civil) - Universidade do Minho, Braga, Portugal, 2016.

DE PAULA, H. M.; RODRIGUES, K. C.; MESQUITA, H. DE C.; EDUARDO, R. C. MapeamentoSistemático de Referências do Uso do BIM na Compatibilização de Projetos na Construçãocivil. REEC - Revista Eletrônica de Engenharia Civil, v. 13, n. 1, 24 mar. 2017.

EASTMAN, C.; TEICHOLZ, P.; SACKS, R.; LISTON, K. Manual de BIM: um guia de modelagem daconstrução para arquitetos, engenheiros, gerentes, construtores e incorporadores. Traduçãode Cervantes Gonçalves Ayres Filho et al. Porto Alegre, RS: BOOKMAN, 2014.

FALBO, Ricardo de Almeida. Mapeamento Sistemático. Disponível em:http://claudiaboeres.pbworks.com/w/file/fetch/133747116/Mapeamento%20Sistem%C3%A1tico%20-%20v1.0.pdf. Acesso em: 02 out. 2019.

CARVALHO, B.; ITO, A.; CARBONI, M.; COIMBRA, C.; SCHEER, S. Uma proposta de método deplanejamento para construções modulares (PMCON). SBTIC 2017. Anais eletrônicos[...].

Ceara-BR, ano 2017, v. 161, p. 348-355, 10 nov. 2017.

GEORGIADOU, M. An overview of benefits and challenges of building information modelling(BIM) adoption in UK residential projects. Construction Innovation. 19 (3), pp. 298-320, 2019.Doi:10.1108/CI-04-2017-0030.

GILSON, R. Maximizing project delivery through BIM coordination and integration. EngineerMagazine and Newletters, 15 Junho 2017. Disponível em:https://www.csemag.com/articles/maximizing-project-delivery-through-bim-coordinationand-integration-2/. Acesso em: 23 nov. 2020.

GLEDSON, B.J.; GREENWOOD, D.J. Surveying the extent and use of 4D BIM in the UK. Itcon, v.

21, pg. 57-71, Jan. 2016. Disponível em:https://www.itcon.org/papers/2016_4.content.02642.pdf. Acesso em: 12 nov. 2020.

GOUVEIA, T. Integração de Ferramentas BIM na Gestão de Obra. 2016. 109 p. Dissertação(Grau de Mestre em Engenharia Civil) - Universidade do Minho, Braga, Portugal, 2016.

HAUBLER, M.; BORRMAN, A. Model-based quality assurance in railway infrastructure planning.

Automation in Construction. Volume 109, 2020, 102971, ISSN 0926-5805.

DOI:https://doi.org/10.1016/j.autcon.2019.102971.

JEONG, W.; CHANG, S.; SON, J.; YI, J.et al. BIM-Integrated Construction Operation Simulationfor Just-In-Time Production Management. Sustainability, Basel, Switzerland, p. 25, 29 out. 2016.

DOI: https://doi.org/10.3390/su11247011.

KAZARYAN, R.; GALAEVA, N.; AVETISYAN, R.; ALIEV, S.Building lifecycle management based on4D modelling as the main workspace for building risk assessment. E3S Web of Conference ,Volume 224, Topical Problems of Agriculture, Civil and Environmental Engineering (TPACEE2020). DOI: doi.org/10.1051/e3sconf/202022402023.

KONYUSHKOV, V.; SOTNIKOV, S.; VERETENNIKOV, V; ERSHOV, I. Application of 4D BIMmodelling in planning and construction of zero cycle works. E3S Web of Conference , Volume164, Topical Problems of Agriculture, Civil and Environmental Engineering (TPACEE 2019). DOI:doi.org/10.1051/e3sconf.

LI, S.; ZHANG, Z.; MEI, G.; LIN, D.; YU, G.; QIU, R.; SU, X.; LIN, X.; LOU, C. Utilization of BIM in theconstruction of submarine tunnel: a case study in xiamen city, china. Journal of CivilEngineering and Management, 2021, v. 27,pág. 14–26.

DOI: doi.org/10.3846/jcem.2021.14098.

LUCARELLI, M; LAURINI, M.; BERARDINIS, P. 3D AND 4D modelling in building site workingcontrol. The International Archives of the Photogrammetry, Remote Sensing and SpatialInformation Sciences, [S. l.], ano 2019, v. XLII-2/W9, 6-8 feb. 2019. DOI: doi.org/10.5194/isprsarchives-XLII-2-W9-441-2019.

MARQUES, A. Planejamento e Controle de Obra Integrado ao Bim, com Foco no Processo deConhecimento. Orientador: Prof.ª Solange da Silva, Drª. 2019. 106 p. Dissertação (Mestre emEngenharia de Produção) - PUC-GO, Goiania, GO, 2019.

MATTOS, Aldo. Planejamento e Controle de Obras. São Paulo: Pini Ltda, 2010. 426 p.

MATOS, C.; MIRANDA, A. The use of Bim in public construction supervision in Brazil. Sciendo,Brasília, BR, v. 10, p. 1761–1769, 10 nov. 2018. DOI: doi.org/10.2478/otmcj-2018-0007.

MATTÉ, G. R. Modelo Interoperável de planejamento e controle do progresso físico de obrasutilizando tecnologia BIM. Orientador: Prof. Dr.-Ing. Malik Cheriaf Florianópolis 2017. 2017. 357p. Dissertação (Grau de Mestre em Engenharia Civil) - UFSC, Florianópolis, SC, 2017.

MAZARS, T; ADEL, F. Chronographical spatiotemporal dynamic 4D planning. Automation inConstruction, Volume 112, 2020, 103076, ISSN 0926-5805. DOI:doi.org/10.1016/j.autcon.2020.103076.

MELHADO, Sílvio Burrattino; SOUZA, Ana Lúcia Rocha de; FONTENELLE, Eduardo; etal. Coordenação de projetos de edificações. Companhia das Rosas, 2005.

MELZNER, Jürgen; HANFF, Jochen. Automatic Generation of 4D-Schedules for reliableConstruction Management. Lake Constance 5D-Conference 2016, [S. l.], p. 112-124, 4 out.2016.

NURSEN, P.; BOONYUNG, W.;NUSEN, S.;PANUWATWANICH, K.; CHAMPRASERT, P.;KAEWMORACHAROEN, M. Construction Planning and Scheduling of a Renovation ProjectUsing BIM-Based Multi-Objective Genetic Algorithm. Appl. Sci. 2021, 11, 4716.https://doi.org/10.3390/app11114716.

RODRIGUES, P. B. de F.; MACHADO, R. L.; MENDES JÚNIOR, R.; ROMAGNOLI, L. D. S. C. Umaproposta de integração do modelo BIM ao sistema last planner. Ambiente Construído, PortoAlegre, v. 18, n. 4, p. 301-317, out./dez. 2018. ISSN 1678-8621 Associação Nacional deTecnologia do Ambiente Construído. http://dx.doi.org/10.1590/s1678-86212018000400306.

SACKS, R.; RADOSAVLJEVIC, M.; BARAK, R. Requirementes For Building Information ModelingBased Lean Production Management Systems FOR construction. Automation in Construction,v. 19. p. 641655, 2010.

SILVA, P. Diretrizes de modelagem da informação da construção (BIM) em projeto eplanejamento de edifícios multipavimentos. Curitiba 2017. 2018. 293 p. Dissertação (Grau deMestre em Construção Civil) - UFPR, CURITIBA, PR, 2018.

SILVA, P; CRIPPA, J.; SCHEER, S. BIM 4D no planejamento de obras: detalhamentos, benefíciose dificuldades. Periódicos Unicamp, Campinas, SP, ano 2019, v. 10, n. e019010, p. 1-13, 26 fev.

2019. DOI: https://doi.org/10.20396/parc.v10i0.8650258.

SMITH, Peter. Project Cost Management with 5D BIM. Procedia - Social and BehavioralSciences, [S. l.], ano 2016, v. 226, p. 193-200, 17 jun. 2016. DOI:https://doi.org/10.1016/j.sbspro.2016.06.179.

TOLEDO, Mauricio; OLIVARES, Katherine; GONZALEZ, Vicente. “Exploration of a Lean-BIMPlanning Framework: A Last Planner System and BIM-Based Case Study.”.2016. In: Proc. 24thAnn. Conf. of the Int’l. Group for Lean Construction, Boston. Anais Eletrônicos[...]. MA, USA,sect.5 pp. 3–12. Disponível em:UCHOA, M. K. Planejamento e Controle de Obras Utilizando Tecnologia BIM. Orientador: Prof.ªDrª. Caroline Maria de Miranda Mota. 2017. 95 f. Dissertação (Mestre em Engenharia deProdução) - UFPE, Recife, 2017.

VELHO, R. Implementação de metodologias BIM e preparação e controlo de obras.

Orientador: Professor Doutor João Pedro da Silva Poças Martins. 2016. 89 p. Dissertação (Graude Mestre em Engenharia Civil) - Universidade do Minho, Braga, Portugal, 2016.

XU, Jiang. Research on Application of BIM 5D Technology in Central Grand Project. ProcediaEngineering, [S. l.], v. 174, p. 600-610, 19 jan. 2017. DOIhttps://doi.org/10.1016/j.proeng.2017.01.194.

Published

2021-11-19

How to Cite

Carneiro, N. ., Carolina Maciel, A. ., Vaz, C. ., & Luís de Araujo, A. . (2021). THE USE OF 4D AND 5D METHODOLOGY FOR WORKS MANAGEMENT AND PLANNING: SYSTEMATIC LITERATURE REVIEW. SIMPÓSIO BRASILEIRO DE QUALIDADE DE PROJETO DO AMBIENTE CONSTRUÍDO, 7, 1–10. https://doi.org/10.29327/sbqp2021.438152

Issue

Section

Inovações tecnológicas e de informação no desenvolvimento do projeto

Similar Articles

<< < 2 3 4 5 6 7 8 9 > >> 

You may also start an advanced similarity search for this article.