Flowchart for integrating time and cost parameters into the BIM model:

a case study

Authors

DOI:

https://doi.org/10.46421/entac.v20i1.5789

Keywords:

BIM, Cost, Planning, Simulation, BIM Integration

Abstract

The current context of technological innovation guides the applicability of the Building Information Modeling (BIM) to simultaneously meet the management of the various project specialties, integrating with the time and cost parameters of the undertaking. Current technological tools and software allow information integration, but the modeling procedures using different programs are only sometimes detailed and systematized. In this context, this study aims to present a flowchart of the procedures necessary to help integrate time and cost into the BIM model, considering the possibilities of project changes. The methodology adopted was the case study of a residence, using specific planning and cost and BIM modeling programs. Three simulation options for the masonry service were performed and compared, considering changes in materials and project scope. The results allowed the validation of the proposed flowchart, thus contributing to systematizing the procedure for integrating the expected time and cost during the project design phase.

Author Biographies

Carlos Francisco Minari Junior, Universidade Federal de São Carlos

Mestre em Construção Civil pela Universidade Federal de São Carlos (2009). Doutorando no Programa de Pós-Graduação em Engenharia Civil na Universidade Federal de São Carlos (São Carlos - SP, Brasil). 

Sheyla Mara Baptista Serra, Universidade Federal de São Carlos

Doutora em Engenharia Civil pela Universidade de São Paulo (2001). Professora Titular do Departamento de Engenharia Civil da Universidade Federal de São Carlos (São Carlos - SP, Brasil).

References

KERN, A.P. Proposta de um modelo de planejamento e controle de custos de empreendimentos de construção. 2005. Tese

(Doutorado em Engenharia Civil) – Universidade Federal do Rio Grande do Sul (UFRGS), Porto Alegre, 2005.

CORRÊA, L.; MARCHIORI, F. 4D BIM na construção civil e sua relação com lean construction: revisão sistemática da literatura. In:

SIMPÓSIO BRASILEIRO DE GESTÃO E ECONOMIA DA CONSTRUÇÃO (SIBRAGEC), 10., 2017. Anais [...] Fortaleza: Universidade Federal

de (UFC), 2017.

SOUZA, N.; CARNEIRO, R. Panorama do uso do BIM 4D E 5D no planejamento e gerenciamento de obras na construção civil. 2019.

f. Trabalho de Conclusão de Curso (Graduação em Engenharia Civil) – Universidade Federal de Uberlândia (UFU), Uberlândia,

EASTMAN, C.; TEICHOLZ, P.; SACKS, R.; LISTON, K. Manual de BIM: um guia de modelagem da construção para arquitetos,

engenheiros, gerentes, construtores e incorporadores. Tradução de Cervantes Gonçalves Ayres Filho et al. Porto Alegre, RS:

Bookman, 2014.

MATOS, P.R.F.; LIMA, M.G.; BARROS NETO, J.P. O uso do BIM no planejamento e controle de prazos e custos: uma revisão

sistemática da literatura. In: SIMPÓSIO BRASILEIRO DE GESTÃO E ECONOMIA DA CONSTRUÇÃO (SIBRAGEC), 12., 2021. Anais [...]

Porto Alegre: ANTAC, 2021. p.1-8. Disponível em: https://eventos.antac.org.br/index.php/sibragec/article/view/427. Acesso em: 2

out. 2023.

SANTOS, M.C.F. Método para integração do orçamento, planejamento e acompanhamento da produção com apoio de Building

Information Modeling. 2018. 209p. Dissertação (Mestrado em Engenharia Civil) – Universidade Federal da Bahia (UFBA), Salvador,

LEE, S.; KIM, K.; YU, J. BIM and ontology-based approach for building cost estimation. Automation in Construction, v.41, p. 96–105,

https://doi.org/10.1016/j.autcon.2013.10.020

CHEN, S.; GRIFFIS, F.H.; CHEN, P.H.; CHANG, L.M. A framework for an automated and integrated project scheduling and

management system. Automation in Construction, v.35, p. 89-110, 2013. https://doi.org/10.1016/j.autcon.2013.04.002

SATTINENI, A.; MACDONALD, J. 5D-BIM: A case study of an implementation strategy in the construction industry. In: International

Symposium on Automation and Robotics in Construction and Mining (ISARC), 31., 2014. Proceedings [...] Sydney: International

Association for Automation and Robotics in Construction (IAARC), 2014, p. 361-367. https://doi.org/10.22260/ISARC2014/0048

LEE, A.; SEXTON, M.G. nD modelling: industry uptake considerations. Construction Innovation, v.7, n.3, p.288-302, 2007. https://

doi.org/10.1108/14714170710754768

BIOTTO, C.N.; FORMOSO, C.T.; ISATTO, E.L. Uso de modelagem 4D e Building Information Modeling na gestão de sistemas de

produção em empreendimentos de construção. Ambiente Construído, v. 15, n. 2, p. 79-96, 2015. https://doi.org/10.1590/

s1678-86212015000200015

VICO. 5D BIM. VICO Software, 2011. Disponível em: https://www.vicosoftware.com/what-is- 5D-BI. Acesso em: 3 de agosto 2023.

PEREIRA, D.M.; FIGUEIREDO, K. O impacto da metodologia BIM na elaboração de orçamentos em projetos de obras civis. Boletim

do Gerenciamento, v. 17, n. 17, p. 30-44, 2020. https://nppg.org.br/revistas/boletimdogerenciamento/article/view/380/281

MILANA, G.S.; FIGUEIREDO, K.V. A Metodologia BIM como fortalecedora do planejamento e controle de obras. Boletim do

Gerenciamento, v. 41, n.41, p. 1-12, 2024. https://nppg.org.br/revistas/boletimdogerenciamento/article/view/1145

EASTMAN, C.; TEICHOLZ, P.; SACKS, R.; LISTON, K. BIM Handbook. A Guide to Building Information Modeling for Owners,

Managers, Designers, Engineers, and Contractors. 2nd ed. John Wiley & Sons, Inc., 2011.

ELSHEIKH, A. Construction workspace management using 4D BIM. AIP Conference Proceedings, v. 2559, n. 1, 040010, 2022.

https://doi.org/10.1063/5.0099410

WANG, L. Using 4D modeling to advance construction visualization in engineering education. Technical Report No. 51. Computer

Integrated Construction Research Program, Pennsylvania State University, 2007. 137p. Disponível em: https://www.engr.psu.edu/

ae/cic/publications/TechReports/TR_051_Wang_2007_4D_Modeling_in_Education.pdf. Acesso em: 12 agosto 2024.

YIN, R.K. Estudo de Caso: planejamento e métodos. 2.ed. Porto Alegre: Bookman, 2001.

Published

2024-10-07

How to Cite

MINARI JUNIOR, Carlos Francisco; SERRA, Sheyla Mara Baptista. Flowchart for integrating time and cost parameters into the BIM model:: a case study. In: NATIONAL MEETING OF BUILT ENVIRONMENT TECHNOLOGY, 20., 2024. Anais [...]. Porto Alegre: ANTAC, 2024. p. 1–15. DOI: 10.46421/entac.v20i1.5789. Disponível em: https://eventos.antac.org.br/index.php/entac/article/view/5789. Acesso em: 24 nov. 2024.