Contribution to the estimate of the duration of convenants for the execution of constructions application in Sudene

application in Sudene

Authors

DOI:

https://doi.org/10.46421/entac.v20i1.5888

Keywords:

Duration forecast, Covenants, Engineering construction

Abstract

The prediction of the duration of an convenant is prerequisite for its signature. However, many times this forecast has low accuracy and ends up resulting in rework related to time additives or even anticipation of accountability. This work seeks to contribute to the forecast of the duration of convenants for execution of engineering constructions by verifying which variables, available until the signature, can explain the variation of the duration, with subsequent forecasting of the model through multiple linear regression, with data from the Brazil’s Northeast Development Superintendence - Sudene. The results sugests that the variables Global Value, Time until the celebration, IDTRV and the types of constructions generate good adjustment and acceptable accuracy in the model and can assist in estimating

Author Biographies

Givanildo Ramos de Souza, Superintendência do Desenvolvimento do Nordeste

Mestrado em Engenharia Civil pela Universidade Federal de Pernambuco

Engenheiro Civil na Superintendência do Desenvolvimento do Nordeste

Arnaldo Manoel Pereira Carneiro, Universidade Federal de Pernambuco

Doutorado em Engenharia Civil pela Universidade de São Paulo.

Professor titular na Universidade Federal de Pernambuco.

References

AFONSO, J.R.R; ARAÚJO, E.A. A capacidade de gasto dos municípios brasileiros: arrecadação própria e receita disponível. Cadernos

de Finanças Públicas. Brasília, v.1, n.1, p. 19-30, 2000.

LOPES, R. G. A.; SETA, M. H.; BATTESINI, M. Análise das transferências financeiras federais para as ações laboratoriais de vigilância

sanitária no Brasil: 2007 a 2016. Vigilância Sanitária em Debate. Rio de Janeiro, v. 7, n. 3, p. 14, 2019.

BRASIL. Portaria Conjunta MGI/MF/CGU nº 33, de 30 de agosto de 2023. Estabelece normas complementares ao Decreto nº 11.531,

de 16 de maio de 2023, que dispõe sobre convênios e contratos de repasse relativos às transferências de recursos da União.

Brasília, 2023. Disponível em: https://www.gov.br/transferegov/pt-br/legislacao/portarias/portaria-conjunta-mgi-mf-cgu-

no-33-de-30-de-agosto-de-2023. Acesso em: 22 de abril de 2024.

BORGES, M. L. F. Causas e Consequências dos Aditivos de Prazos nos Contratos Públicos - Caso de uma Ciclovia. 2020. 110f.

Dissertação (mestrado em Engenharia Civil) - Universidade Fernando Pessoa, Porto, 2020.

VARGAS, R. Gerenciamento de Projetos: Estabelecendo Diferenciais Competitivos. 6a ed. Rio de Janeiro: Brasport, 2005.

BRANDALISE, D. A importância do gerenciamento do tempo em projetos de construção civil. 2017. 57f. Monografia (Especialização

em Gerenciamento de Projetos) - Fundação Getúlio Vargas, Rio de Janeiro, 2017.

AGYEKUM-MENSAH, G.; KNIGHT, A. D. The professionals’ perspective on the causes of project delay in the construction industry.

Engineering, Construction and Architectural Management. v. 24, n. 5, p. 828-841, 2017.

NG, S. T.; MAK, M. M. Y.; SKITMORE, R. M.; LAM, K. C.; VARNAM, M. The predictive ability of Bromilow's time-cost model.

Construction Management and Economics, v.19, n.2, p. 165-173, 2001. DOI: https://doi.org/10.1080/01446190150505090

SONGER, A. D.; MOLENAAR, K. R. Project Characteristics for Successful Public-Sector Design Build. Journal of Construction

Engineering and Management, n. 123, p. 34-40, 1997.

A. CZARNIGOWSKA, A. SOBOTKA. Time–cost relationship for predicting construction duration. Archives of Civil and Mechanical

Engineering, v. 13, n. 4, p. 518-526, dez. 2013. DOI: https://doi.org/10.1016/j.acme.2013.05.004

LOPES, C. P. A. Uma análise sobre os aditivos de contratos em obras rodoviárias no Estado do Ceará. 2017. 115f. Dissertação

(Mestrado em Engenharia de Transportes - Universidade Federal do Ceará, Fortaleza, 2017.

MATTEI, T. F.; BEZERRA, F. M.; MELLO, G. R. DE. Despesas públicas e o nível de desenvolvimento humano dos estados brasileiros:

uma análise do IDHM 2000 e 2010. RACE - Revista de Administração, Contabilidade e Economia. Joaçaba, v. 17, n. 1, p. 29–54, 2018.

PNUD, Ipea, FJP. Índice de Desenvolvimento Humano Municipal Brasileiro. Brasília: PNUD, Ipea, FJP, 2013.

GUJARATI , PORTER, D. C. Econometria Básica. 5ª ed., Porto Alegre: Mc Graw Hill, 2011.

HARKNESS, J. COLDIAG: Stata module to perform BWK regression collinearity diagnostics. 2000.

CARMO, C. R. S. Mercado brasileiro de créditos: um estudo sobre seus determinantes e possíveis impactos de variáveis externas,

dentre elas, a crise econômica de 2008-2009. Revista Linkania. Uberlândia, ed. 10, v. 1, p. 13–38, 2014.

MIRANDA, V. F. L. Avaliação Monte Carlo de testes assintóticos e de bootstrap para autocorrelação residual. 2004. 77f. Dissertação

(mestrado em Agronomia) - Universidade Federal de Lavras, Minas Gerais, 2004.

Published

2024-10-07

How to Cite

SOUZA, Givanildo Ramos de; CARNEIRO, Arnaldo Manoel Pereira. Contribution to the estimate of the duration of convenants for the execution of constructions application in Sudene: application in Sudene. In: NATIONAL MEETING OF BUILT ENVIRONMENT TECHNOLOGY, 20., 2024. Anais [...]. Porto Alegre: ANTAC, 2024. p. 1–14. DOI: 10.46421/entac.v20i1.5888. Disponível em: https://eventos.antac.org.br/index.php/entac/article/view/5888. Acesso em: 22 nov. 2024.

Similar Articles

<< < 20 21 22 23 24 25 26 27 28 29 > >> 

You may also start an advanced similarity search for this article.