Physical Flows Continuity and Stability – a Chimera in Lean Construction Applications?

Authors

DOI:

https://doi.org/10.46421/entac.v20i1.6356

Keywords:

Lean Construction, Workflow, Work Sequence, Process Stability

Abstract

For a long time, it has been demonstrated that repetitive construction sites are characterized by discontinuity in the production flow, lack of sequence, and significant variability in resource utilization. Lean production implementations in construction sites have focused on metrics such as constraint removal, Planned Percentage Completion (PPC), and deviations from schedule, without yet delving into more operational measures reflecting production aspects of their operations as illustrated by flow diagrams, flowcharts, and man-machine diagrams. This article reviews recent literature illustrating that, in most cases, there is still discontinuity, lack of sequence, and instability in the production flow. The work brings together evidence from the experience of three construction sites, corroborating the review of the bibliography regarding the difficulties in implementing flow concepts on site.

Author Biographies

Mayana Chagas Carvalho, Instituto Federal da Paraíba

Mestrado em Engenharia Civil pela Universidade Federal de Sergipe. Técnica de Laboratório em edificações no Instituto Federal de Educação, Ciência e Tecnologia da Paraíba (Catolé do Rocha - PB, Brasil).

Débora de Gois Santos, Universidade Federal de Sergipe

He holds a degree in Civil Engineering from the Federal University of Sergipe (1998) (UFS), a master's degree in Civil Engineering (2000) and a PhD in Production Engineering from the Federal University of Santa Catarina (2004) (UFSC). She is currently Associate Professor 4 at the Department of Civil Engineering at UFS and a journal reviewer. at UFS, she was Head of Department and Coordinator of the Civil Engineering course at UFS (2009-2011), Director of Extension (2013-2014), Coordinator of the Postgraduate Program in Civil Engineering (2016-2018). At ANTAC, she served as Coordinator of the Construction Management and Economics GT (2019-2021), Director of Interinstitutional Relations (2020-2022) and Coordinated the XII SIBRAGEC and IV SBTIC in 2023. She was a Member of the Study Committee for the standard of ABNT Building Guarantee (CE 02.140.003). She is currently Coordinator of the Civil Construction Laboratory (LACC) at UFS and Member of the Materials Committee at Aseopp - Technical Standards Study Group. He has experience in the area of ​​Civil Engineering, with an emphasis on Construction Management, working mainly on the following topics: lean construction, building performance standards and waste management.

Luiz Fernando Mahlmann Heineck, Universidade Estadual do Ceará

Pós-doutor em Economia da Construção e Habitação pela Universidade de Utrecht. Professor adjunto Centro de Estudos Sociais Aplicados da Universidade Estadual do Ceará (Fortaleza - CE, Brasil).

Antônio Nunes de Miranda Filho, Universidade Federal do Ceará

He obtained a PhD in Industrial Engineering and Management from the University of Porto (2009), a Master's degree in Production Engineering from the Federal University of Santa Catarina (2001) and a Bachelor's degree in Civil Engineering from the Federal University of Ceará (1998). He is currently a Visiting Professor at the Postgraduate Program in Civil Engineering at the Federal University of Ceará (UFC), where he teaches the subjects of Quality and Productivity and Fundamentals for Project-Based Organizations. He has business experience in the areas of Production Engineering and Business Administration, having been technically responsible for large residential and commercial projects in the Civil Construction Industry. He has extensive experience with the implementation of Lean Management Systems and Quality Management in companies. He also has experience in managing development projects, having even coordinated the UFC, FIEC and Ceará State Government teams in studies for the implementation of the Green Hydrogen HUB in Ceará. It has participated in the Ceará Civil Construction Innovation Program (INOVACON-CE) and the Civil Construction Cooperative of the State of Ceará (COOPERCON-CE) since its foundations. He has focused his research mainly on Project-Based Organizations, developing studies on the following topics: (I) production and operations management; (II) lean production; (III) project management; (IV) systems theory; and (V) strategy and organizational structure.

References

KANKAINEN, J.; SEPPÄNEN, O. A Line-of-Balance Based Schedule Planning and Control System. In: INTERNATIONAL GROUP FOR

LEAN CONSTRUCTION, 11, Virginia, 2003. Proceedings [...] Virginia: IGLC, 2003, p. 132-143.

POWER, W.; SINNOTT, D.; LYNCH, P. An Examination of IGLC Takt Literature - Learnings & Opportunities. In: INTERNATIONAL

GROUP FOR LEAN CONSTRUCTION, 31, Lille, 2023. Proceedings [...] Lille: IGLC, 2023, p. 1557-1569. doi.org/10.24928/2023/0218

HAGHSHENO, S.; BINNINGER, M.; DLOUHY, J.; STERLIKE, S. History and Theoretical Foundations of Takt Planning and Takt Control. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 24, Massachusetts, 2016. Proceedings [...] Massachusetts: IGLC, 2016, p. 53-62.

LUMSDEN, P., The Line of Balance Method, Pergamon Press, Industrial Training Division, Oxford, 1968, 71 p.

BERTELSEN, S.; KOSKELA, L. Avoiding and Managing Chaos in Projects. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 11,

Virginia, 2003. Proceedings [...] Virginia: IGLC, 2003.

SEPPANEN, O.; KANKAINEN, J. Empirical Research on Deviations in Production and Current State of Project Control. In:

INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 12, Helsingør, 2004. Proceedings [...] Helsingør: IGLC, 2004.

KENLEY, R. Dispelling the Complexity Myth: Founding Lean Construction on Location-Based Planning. In: INTERNATIONAL GROUP

FOR LEAN CONSTRUCTION, 13, Sydney, 2005. Proceedings [...] Sydney: IGLC, 2005, p. 245-251.

WU, J.; SOIBELMAN, L. Graphical Analysis on Non-Conformances of Construction Production Processes: Ongoing Research and

Case Study. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 14, Santiago, 2006. Proceedings [...] Santiago: IGLC, 2006, p.

-405.

AL-SUDAIRI, A. A.; DIEKMANN, J. E.; SONGER, A. D.; BROWN, H. M. Simulation of Construction Processes: Traditional Practices

Versus Lean Principles. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 7, California, 1999. Proceedings [...] California:

IGLC, 1999, p. 39-50.

MENDEZ, JR., R.; HEINECK, L. F. M. Preplanning Method for Multi-Story Building Construction Using Line of Balance. In:

INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 6, Guarujá, 1998. Proceedings [...] Guarujá: IGLC, 1998.

ROCHA, C. G.; WIJAYARATNA, K.; KOSKELA, L. Why Is Flow Not Flowing in the Construction Industry? In: INTERNATIONAL GROUP

FOR LEAN CONSTRUCTION, 30, Edmonton, 2022. Proceedings [...] Edmonton: IGLC, 2022, p. 283-294. doi.org/10.24928/2022/0130

APGAR, B.; SMITH, J. P. Do Failures in a Takt Plan Fit the FMEA Framework? In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION,

, Lille, 2023. Proceedings [...] Lille: IGLC, 2023, p. 1383-1394. doi.org/10.24928/2023/0246

LEHTOVAARA, J.; TOMMELEIN, I. D.; SEPPÄNEN, O. How a Takt Plan Can Fail: Applying Failure Modes and Effects Analysis in Takt

Control. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 30, Edmonton, 2022. Proceedings [...] Edmonton: IGLC, 2022, p.

-726. doi.org/10.24928/2022/0182

GÖRSCH, C.; AL BARAZI, A.; SEPPÄNEN, O.; ABOU IBRAHIM, H. Uncovering and Visualizing Work Process Interruptions Through

Quantitative Workflow Analysis. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 30, Edmonton, 2022. Proceedings [...]

Edmonton: IGLC, 2022, p. 142-152. doi.org/10.24928/2022/0116

BINNINGER, M.; DLOUHY, J.; HAGHSHENO, S. Flow in Takted Projects – A Practical Analysis of Flow and Resource Efficiency. In:

INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 27, Dublin, 2019. Proceedings [...] Dublin: IGLC, 2019, p. 1271-1282.

doi.org/10.24928/2019/0228

SEPPÄNEN, O.; EVINGER, J.; MOUFLARD, C. 2013. Comparison of LBMS Schedule Forecasts to Actual Progress. In: INTERNATIONAL

GROUP FOR LEAN CONSTRUCTION, 21, Fortaleza, 2013. Proceedings [...] Fortaleza: IGLC, 2013, p. 569-578.

ALHAVA, O.; RINNE, V.; LAINE, E.; KOSKELA, L. Can a Takt Plan Ever Survive Beyond the First Contact With the Trades On-Site? In:

INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 27, Dublin, 2019. Proceedings [...] Dublin: IGLC, 2019, p. 453-464.

doi.org/10.24928/2019/0261

MURGUIA, D.; RATHNAYAKE, A.; MIDDLETON, C. Master Schedule Optimisation With the Use of Flowlines and Performance Data.

In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 31, Lille, 2023. Proceedings [...] Lille: IGLC, 2023, p. 1463-1474.

doi.org/10.24928/2023/0121

SEPPÄNEN, O.; MODRICH, R.; BALLARD, G. Integration of Last Planner System and Location-Based Management System. In:

INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 23, Perth, 2015. Proceedings [...] Perth: IGLC, 2015, p. 123-132.

KOSKELA, L.; HOWELL, G.; PIKAS, E.; DAVE, B. If CPM Is So Bad, Why Have We Been Using It So Long. In: INTERNATIONAL GROUP

FOR LEAN CONSTRUCTION, 22, Oslo, 2014. Proceedings [...] Oslo: IGLC, 2014, p. 27-37.

BATAGLIN, F. S.; VIANA, D. D.; COELHO, R. V.; TOMMELEIN, I. D.; FORMOSO, C. T. Buffer Types and Methods of Deployment in

Construction. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 29, Lima, 2021. Proceedings [...] Lima: IGLC, 2021, p.

-858. doi.org/10.24928/2021/0171

POSHDAR, M.; GONZÁLEZ, V. A.; BELAYUTHAM, S. An Inclusive Probabilistic Buffer Allocation Method. In: INTERNATIONAL GROUP

FOR LEAN CONSTRUCTION, 23, Perth, 2015. Proceedings [...] Perth: IGLC, 2015, p. 183-192.

HARONIAN, E.; KORB, S.; Towards a Flow-Based Disruption Metric: A Case Study. In: INTERNATIONAL GROUP FOR LEAN

CONSTRUCTION, 31, Lille, 2023. Proceedings [...] Lille: IGLC, 2023, p. 344-352. doi.org/10.24928/2023/0212

PRIVEN, V.; SACKS, R.; SEPPÄNEN, O.; SAVOSNICK, J. A Lean Workflow Index for Construction Projects. In: INTERNATIONAL GROUP

FOR LEAN CONSTRUCTION, 22, Oslo, 2014. Proceedings [...] Oslo: IGLC, 2014, p. 715-726.

SINGH, V. V.; TOMMELEIN, I. D. Workload Leveling Metrics for Location-Based Process Design. In: INTERNATIONAL GROUP FOR

LEAN CONSTRUCTION, 31, Lille, 2023. Proceedings [...] Lille: IGLC, 2023, p. 1593-1604. doi.org/10.24928/2023/0244

BINNINGER, M.; DLOUHY, J.; MÜLLER, M.; SCHATTMANN, M.; HAGHSHENO, S. Short Takt Time in Construction – a Practical Study.

In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 26, Chennai, 2018. Proceedings [...] Chennai: IGLC, 2018, p. 1133-1143.

doi.org/10.24928/2018/0472

LEHTOVAARA, J.; HEINONEN, A.; LAVIKKA, R., RONKAINEN, M.; KUJANSUU, P., RUOHOMÄKI, A.; ÖRMÄ, M.; SEPPÄNEN, O.;

PELTOKORPI, A. Takt Maturity Model: from individual Successes towards Systemic Change in Finland. In: INTERNATIONAL GROUP

FOR LEAN CONSTRUCTION, 28, Berkeley, 2020. Proceedings […] Berkeley: IGLC, 2020, p. 433-444. doi.org/10.24928/2020/0017

BRODETSKAIA, I.; SACKS, R. Understanding Flow and Micro-Variability in Construction: Theory and Practice. In: INTERNATIONAL

GROUP FOR LEAN CONSTRUCTION, 15, East Lansing, 2007. Proceedings [...] East Lansing: IGLC, 2007, p. 488-497.

GUPTA, A.; DEVKAR, G. Investigating Emergence of ‘New Tasks’ in Last Planner® System: Social Network Perspective of Planning

Behaviours. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 31, Lille, 2023. Proceedings [...] Lille: IGLC, 2023, p. 1314-1325.

doi.org/10.24928/2023/0208

SANTOS, D. G.; GROSSKOPF, J.; SOUZA, A. M.; SANTOS NETO, A. T. D.; HEINECK, L. F. M. Utilization of Extra Planning Activities by

Construction Companies in Sergipe, Brazil. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 20, San Diego, 2012.

Proceedings [...] San Diego: IGLC, 2012.

KOSKELA, L. Making-Do — the Eighth Category of Waste. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 12, Helsingør,

Proceedings [...] Helsingør: IGLC, 2004.

FAZINGA, W. R.; SAFFARO, F. A.; ISATTO, E. L.; KREMER, A. Difficulties in Work Design in the Construction Sector. In:

INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 24, Massachusetts, 2016. Proceedings [...] Massachusetts: IGLC, 2016.

REBAI, S.; ALBALKHY, W.; HAMDI, O.; LAFHAJ, Z. Lean Construction and AWP: Similarities, Differences and Opportunities. In:

INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 31, Lille, 2023. Proceedings [...] Lille: IGLC, 2023, p. 1428-1439.

doi.org/10.24928/2023/0258

MILBERG, C. Tolerance Considerations in Work Structuring. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 15, East

Lansing, 2007. Proceedings [...] East Lansing: IGLC, 2007, p. 233-243.

HALTTULA, H. P. I.; SEPPÄNEN, O. Situational Awareness in Construction Projects Using Takt Production. In: INTERNATIONAL

GROUP FOR LEAN CONSTRUCTION, 30, Edmonton, 2022. Proceedings [...] Edmonton: IGLC, 2022, p. 164-174.

doi.org/10.24928/2022/0119

PIKAS, E.; SACKS, R.; PRIVEN, V. Go or No-Go Decisions at the Construction Workface: Uncertainty, Perceptions of Readiness,

Making Ready and Making-Do. In: INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 20, San Diego, 2012. Proceedings [...] San

Diego: IGLC, 2012.

ANDREASSEN, M.; DREVLAND, F. Handoffs Between Takt Train Wagons: a Systematic Literature Review. In: INTERNATIONAL

GROUP FOR LEAN CONSTRUCTION, 31, Lille, 2023. Proceedings [...] Lille: IGLC, 2023, p. 1487-1497. doi.org/10.24928/2023/0130

HEINECK, L. F. Some causes of the variability of the level of resources assigned to building sites programmes of work. 1982.

Internal Report - Department of Civil Engineering, University of Leeds, England, 1982. Disponível em: https://lume.ufrgs.br/

bitstream/handle/10183/149130/001002552-02.pdf?sequence=2&isAllowed=y Acesso em: 20 abr 2024.

HEINECK, L. F. On the analysis of activity durations, precedence and sequence of work on housebuilding sites of repetitive nature –

graphical software to enhance the printed output from the Building Research Establishment Site Analysis Package. Internal

Report - Department of Civil Engineering, University of Leeds, England, 1982. Disponível em: https://lume.ufrgs.br/bitstream/

handle/10183/149019/000011837.pdf?sequence=1 Acesso em: 20 abr 2024.

HEINECK, L. F. The examination of possible causes of the lack of success in the application of programming techniques to building

sites. 1982. Internal Report - Department of Civil Engineering, University of Leeds, England, 1982. Disponível em: https://

lume.ufrgs.br/bitstream/handle/10183/149130/001002552-03.pdf?sequence=3&isAllowed=y Acesso em: 20 abr 2024.

HEINECK, L. F. On the analyses of activity durations on three house building sites. 1983. 275f. Thesis (PhD. in Civil Engineering) -

Department of Civil Engineering, University of Leeds, England, 1983. Disponível em: https://lume.ufrgs.br/bitstream/

handle/10183/149019/000011837.pdf?sequence=1 Acesso em: 20 abr 2024.

COMMITTEE ON HOUSING, BUILDING AND PLANNING, ECONOMIC COMMISION FOR EUROPE, UNITED NATIONS. Effect of

Repetition on Building Operations and Processes on Site – report of an Inquiry undertaken by the Committee on Housing,

Building and Planning, New York, United Nations, 1965.

SHANLEY, L. F.; KEANEY, B. J. An Examination of Labour Content in Housing. Ann Foras Forbartha, Dublin, Ireland, May 1970.

RODERICK, I. F. Examination of the Use of Critical Path Methods in Building. Building Research Establishment Current Paper n.

/77, BRE, Garston, U.K., March 1977.

HEINECK, L. F. M. Curvas de Agregação de Recursos no Planejamento e Controle da Edificação – aplicação a obras e a programas

de construção. Caderno de Engenharia CE-31/89, Curso de Pós-graduação em Engenharia Civil, Universidade Federal do Rio

Grande do Sul, Porto Alegre, RS, 49p., 1989.

VERAS, V. C. de P.; MIRANDA FILHO, A. N. de; HEINECK, L. F. M.; BERTINI, A. A. Trabalho aprovado. In: ENCONTRO NACIONAL DE

TECNOLOGIA DO AMBIENTE CONSTRUÍDO, 20, Alagoas, 2024 Anais [...] Alagoas: ENTAC, 2024.

Published

2024-10-07

How to Cite

CARVALHO, Mayana Chagas; SANTOS, Débora de Gois; HEINECK, Luiz Fernando Mahlmann; MIRANDA FILHO, Antônio Nunes de. Physical Flows Continuity and Stability – a Chimera in Lean Construction Applications?. In: NATIONAL MEETING OF BUILT ENVIRONMENT TECHNOLOGY, 20., 2024. Anais [...]. Porto Alegre: ANTAC, 2024. p. 1–12. DOI: 10.46421/entac.v20i1.6356. Disponível em: https://eventos.antac.org.br/index.php/entac/article/view/6356. Acesso em: 19 oct. 2024.

Issue

Section